  • Question 681:

    Which level of management sets the project level tolerances?

    A. Project board

    B. Team manager

    C. Corporate, programme management or the customer

    D. Project manager

  • Question 682:

    Identify the missing word in the following sentence.

    A project's [ ? ] are the measurable improvements resulting from the outcomes achieved through the use of the project's outputs.

    A. benefits

    B. dis-benefits

    C. issues

    D. risks

  • Question 683:

    Which is a minimum requirement for applying the plans theme?

    A. The project must have at least two management stages

    B. The team managers in the project must prepare team plans

    C. Scope tolerance must be prioritized using MoSCoW

    D. The project plan must be presented as a Gantt chart

  • Question 684:

    Which theme estimates the cost of delivering the project?

    A. Business case

    B. Change

    C. Plans

    D. PROGEESS

  • Question 685:

    How does the use of product descriptions support the 'focus on products' principle?

    A. By documenting the scope tolerance for the project

    B. By documenting the quality expected by the customer

    C. By documenting the costs for the product

    D. By documenting the delivery date for the product

  • Question 686:

    Which is a purpose of the 'directing a project' process?

    A. To exercise overall control over the project

    B. To take corrective action to control risks and issues

    C. To do the minimum in order to decide whether the project is feasible

    D. To update the project plan before the next stage

  • Question 687:

    Which is a step in the recommended approach to 'defining and analyzing the products'?

    A. Preparing estimates

    B. Designing a plan

    C. Writing a project product description

    D. Identifying activities and dependencies

  • Question 688:

    Which process is used to define how baselines will be established and controlled?

    A. Controlling a stage

    B. Directing a project

    C. Initiating a project

    D. Starting up a project

  • Question 689:

    Which risk response is applied on a pain/gain basis?

    A. Share

    B. Accept

    C. Exploit

    D. Enhance

  • Question 690:

    To meet the minimum requirements for applying the progress theme, what must be considered?

    A. How lessons will be learned

    B. How time-driven reports will be produced

    C. Which management products will be baselined

    D. Who is responsible for reporting on progress

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.