During which process would the stage tolerances be set?
A. Controlling a Stage
B. Initiating a Project
C. Managing a Stage Boundary
D. Directing a Project
Which of the following is not a factor to consider when determining the length of a stage?
A. The amount of resources available h the short term
B. How far ahead you can sensibly plan n detail
C. The technical stages within the project
D. The amount of risk associated with the project
Which statement is TRUE with regard to technical stages?
A. Technical stages can only occur sequential
B. Technical stages define where management decisions are appropriate
C. Technical stages often overlap
D. Technical stages define the commitment of resources and authority to spend
There are two time driven controls in PRINCE2, which are they?
A. Highlight and End Stage Reports
B. Highlight and Checkpoint Reports
C. Checkpoint and End Project Reports
D. Highlight and Lessons Reports
When examining a project issue, which three aspects should be considered?
1.
Performance targets
2.
Business Case
3.
Resources
4.
Risk
A. 1, 3, 4
B. 2, 3, 4
C. 1, 2, 4
D. 1, 2, 3
Who would be responsible for maintaining the Configuration Item Records?
A. Project Manager
B. Project Support
C. Project Assurance
D. Team Manager
If Project tolerances were threatened, who needs to be notified?
A. Project Board
B. Project Manager
C. Corporate or Programme Management
D. Executive
Which of the following statements best describes what a risk owner is?
A. Best placed to keep an eye on the risk
B. Carry out the response actions to a risk
C. Responsible for management, monitoring and control of all aspects of a risk
D. Reports to the project manager regularly on the status of a risk
Who is responsible for reviewing the risk management practices to ensure they are in line with the project's risk management strategy?
A. Project Support
B. Project Manager
C. Team Manager
D. Project Assurance
Which of the following is the definition for an off-specification?
A. An issue the Project Manager needs to resolve or escalate
B. Something forecast or currently not meeting specification
C. A proposal for a change to a baseline
D. A statement of concern
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-PRACTITIONER exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.