A network engineer must configure a Fibre Channel interface on the Cisco MDS 9000 Series Switch The configuration must meet these requirements
1.
The interface must be disabled when the bit errors threshold Is exceeded
2.
Buffer-to-buffer credits must be set to the maximum value
3.
The interface must have full bandwidth allocated for its port group
Which command set configures a Fibre Channel interface that meets these requirements?
A. interface fc1/1 switchport bit-errors switchport fcrxbbcredit 220 mode Fx switchport rate-mode dedicated
B. interface fc1/1 switchport ignore bit-errors switchport fcrxbbcredit 255 mode Fx no switchport rate-mode
C. interface fc1/1 no switchport ignore bit-errors switchport fcrxbbcredit 255 mode Fx switchport rate-mode dedicated
D. interface fc1/1 no switchport bit-errors switchport fcrxbbcredit 220 mode Fx no switchport rate-mode
Refer to the exhibit.
An engineer must configure a Fibre Channel device alias named TEST for a device attached to port fc1/9 of a Cisco Nexus Series Switch. Which command set completes the configuration?
A. Option A
B. Option B
C. Option C
D. Option D
A company plans to migrate some of its services to the cloud. The company does not want to manage or control the underlying cloud infrastructure. It also wants to maintain control over the deployment of its applications and configuration settings of the application-hosting environment. Which cloud service model meets these requirements?
A. Infrastructure as a Service
B. Function as a Service
C. Platform as a Service
D. Software as a Service
Refer to the exhibit.
A network engineer configures the VXLAN between the routers in a data center. The VLAN 10 must be extended between routers A and B. The initial VXLAN configuration is completed on Router A. Which configuration finishes the VXLAN configuration on Router A?
A. Option A
B. Option B
C. Option C
D. Option D
Refer to the exhibit.
An engineer is configuring a Cisco MDS 9000 Series Switch for the first time. After the initial setup process, the name server at IP 192.168.10.11 is missing from the configuration. Which set of actions completes the configuration?
A. Enter no at step 21 and reinitialize the installer. Press the Esc key to access ROMMON mode.
B. Enter no at step 21 and reload the switch. Configure the advanced IP options.
C. Enter yes at step 21 to edit the configuration. Add the line dns-server 192.168.10.11.
D. Enter yes at step 21 and log in. Modify the startup configuration DNS
Refer to the exhibit.
A network engineer is using tcpdump to capture a snapshot of OSPF-related traffic on a specific Cisco NX-OS switch port. For security reasons, the capture must be taken using an embedded container that is already deployed on the Cisco Nexus device. Which command completes the script?
A. guestshell
B. guestshell-bash
C. run guestshell
D. run bash
A network architect must design an automation solution to initially support networking and also support the server infrastructure in the future. To keep configuration consistency, the network team requires a solution that enforces the desired state of the network and reverts any manual configuration. Which solution meets these goals?
A. NX-API
B. Ansible
C. Terraform
D. Puppet
An engineer must integrate Cisco ACI with a VMware vSphere environment. The requirement is to use a VMware Distributed Virtual Switch and to assign the encapsulation VLAN of the EPG from the VLAN pool. Which configuration set accomplishes this goa?
A. Create a VMM domain association under the EPGs Create a VLAN pool with static alocated VLANs.
B. Create a physical domain association under the EPGs Create a VLAN pool with static alocated VLANs.
C. Create a physical domain association under the EPGs. Create a VLAN pool with oVnarmc alocated VLANs
D. Create a VMM domain association under the EPGs Create a VLAN pool with dynamic alocated VLANs.
A network engineer must migrate a Cisco WSA virtual appliance from one physical host to another physical host by using VMware vMotion. What is a requirement for both physical hosts?
A. The hosts must run Cisco AsyncOS 10.0 or greater.
B. The hosts must have access to the same defined network.
C. The hosts must run different versions of Cisco AsyncOS.
D. The hosts must use a different datastore than the virtual appliance
An engineer deploys a new Cisco Nexus 5000 Series Switch in an existing environment with strict security policies. The new device should meet these requirements:
1.
Secure end-user ports with minimum configuration effort.
2.
Log security breaches and require manual recovery.
3.
Retain the switch configuration if the device restarts.
Which configuration must be used?
A. switchport port-security switchport port-security max 1 switchport port-security mac-address sticky
B. switchport port-security switchport port-security violation restrict switchport port-security mac-address sticky
C. switchport port-security switchport port-security violation shutdown switchport port-security mac-address dynamic
D. switchport port-security switchport port-security max 1 switchport port-security violation shutdown
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Cisco exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your 350-601 exam preparations and Cisco certification application, do not hesitate to visit our Vcedump.com to find your solutions here.