A company must implement sales software because it is opening a new branch in a foreign market. Although this software is used in every domestic branch, multiple changes are expected during the implementation because it is a foreign location.
Which type of life cycle would the project manager use in this case?
A. Predictive life cycle
B. Waterfall life cycle
C. Hybrid life cycle
D. Product life cycle
Which of the following lists represents the outputs of the Monitor Communications process?
A. Project communications, project management plan updates, project documents updates, and organizational process assets updates
B. Work performance information, change requests, project management plan updates, and project documents updates
C. Communications management plan, project management plan updates, work performance report, and project documents update
D. Stakeholder engagement plan, change requests, project management plan updates, and project documents updates
How can a project manager evaluate project team development?
A. Produce team performance assessments
B. Hold weekly meetings to engage every member
C. Complete a personal skill assessment on each team member
D. Provide recognition awards to team members
What is a tailoring consideration in Project Integration Management?
A. Validation and control
B. Benefits
C. Technology support
D. Physical location
Which term refers to the work performed to deliver results with specified features and functions?
A. Project scope
B. Product scope
C. Change request
D. Acceptance criteria
What is a tool or technique used in the Control Quality process?
A. Attribute sampling
B. Parametric estimating
C. Statistical sampling
D. Expert judgment
What should a project manager use to determine how much money is needed to complete a project?
A. Earned value management (EVM)
B. Estimate at completion (EAC)
C. Earned value analysis (EVA)
D. Budget at completion (BAG)
What is a tailoring consideration for the application of Project Risk Management processes?
A. Project complexity
B. Procurement criteria
C. Communication technology
D. Knowledge management
A project team conducts regular standup meetings to keep everyone updated on what each one of them is working on. What type of communication is this?
A. Informal
B. Unofficial
C. Formal
D. Hierarchical
What process is included in Project Schedule Management?
A. Estimate Activity Durations
B. Create Work Breakdown Structure (WBS)
C. Direct and Manage Project Work
D. Estimate Activity Resources
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.