What is the discipline that focuses on the interdependences between projects to determine the optimal approach for managing them?
A. Project Management
B. Program Management
C. Portfolio Management
D. Operations Management
A project manager Is addressing risks and potential concerns related to stakeholder management, and Is clarifying and resolving previously Identified issues. In which process is the project manager engaged?
A. Identify Stakeholders
B. Plan Stakeholder Engagement
C. Manage Stakeholder Engagement
D. Monitor Slakeholder Engagement
Which of the following is an example of facit knowledge?
A. Risk register
B. Project requirements
C. Expert judgment
D. Make-or-buy analysis
What does expert judgment provide as an input to the resource management plan?
A. Geographic distribution of facilities and resources
B. Physical resource management policies and procedures
C. Estimated lead times based on lessons learned
D. Templates for the resource management plan
Which process is engaged when a proiect learn inember makes a change to project budget with the project manager's approval?
A. Manage Cost Plan
B. Estimate Costs
C. Determine Budget
D. Control Costs
What purpose does the hierarchical locus of stakeholder communications serve?
A. Maintains the focus on project and organizational stakeholders
B. Preserves the tocus on external stakeholders--such as customers and vendors--as well as on other projects
C. Sustains the focus on general communication activities using email, social media, and websites
D. Keeps the focus on the position of the stakeholder or group with respect to the project team
A team was hired to develop a next generation drone. The team created a prototype and sent it to the customer for testing. The feedback collected was used to refine the requirements. What technique is the team using?
A. Early requirements gathering
B. Feedback analysis
C. Progressive elaboration
D. Requirements documentation
What is the project manager's responsibility in Project Integration Management?
A. Ensuring that requirements-related work is clarified in the project management plan
B. Investing sufficient effort in acquiring, managing, motivating, and empowering the project team
C. Combining the results in all other knowledge areas, and overseeing the project as a whole
D. Developing a strategy to ensure effective stakeholder communication
At what stages of a project should the Identify Stakeholders process be performed?
A. When beginning each phase of the project
B. At the beginning of the project only
C. Only when the project manager is concerned about stakeholder satisfaction
D. When the project charter is produced, at the beginning of each phase, and when significant changes occur
Which components of the project can be updated as a result of managing stakeholder engagement?
A. Project management plan, project documents, and change requests
B. Project management plan, communication plan, and work performance information
C. Risk and communication plans
D. No components of the project can be updated after a stakeholder engagement plan has been completed
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.