  • Question 441:

    Scope verification is PRIMARILY concerned with which of the following?

    A. Acceptance of the work deliverables.

    B. Accuracy of the work deliverables.

    C. Approval of the scope statement.

    D. Accuracy of the work breakdown structure.

  • Question 442:

    Soft logic is also known as what type of dependency?

    A. External

    B. Discretionary

    C. Mandatory

    D. Internal

  • Question 443:

    Team performance assessments is an output of which of the following processes?

    A. Develop Human Resource Plan

    B. Perform Quality Control

    C. Develop Project Team

    D. Manage Project Team

  • Question 444:

    Project Management Process Groups are linked by:

    A. the outputs they produce

    B. discrete or one-time events

    C. the project management plan

    D. common tools and techniques

  • Question 445:

    Project management processes are:

    A. Static; they must not change across different projects.

    B. Applied globally and across all industry groups.

    C. Discrete elements with well-defined interfaces.

    D. Project phases, applied as required in different projects.

  • Question 446:

    Projects are authorized by which of the following individuals?

    A. Project managers

    B. Stakeholders

    C. Functional managers

    D. Sponsors

  • Question 447:

    Projects can intersect with an organization's operations at various points during the product life cycle such as:

    A. When there is an operations shutdown (i.e. a strike).

    B. When developing new products, upgrading products, or expanding outputs.

    C. When a project transitions from a temporary to a permanent status.

    D. When the project manager is promoted to operations manager.

  • Question 448:

    Quality and credibility of the qualitative risk analysis process requires that different levels of the risk's probabilities and impacts be defined is the definition of what?

    A. Risk breakdown structure (RBS)

    B. Risk probability and impact

    C. Qualitative risk analysis

    D. Risk response planning

  • Question 449:

    Schedule milestones and a predefined budget are examples of:

    A. Project constraints.

    B. Requirements documentation.

    C. Organizational process assets.

    D. Activity cost estimates.

  • Question 450:

    Outputs from constituent processes might be used as: A. Inputs to other processes.

    B. Proof of process completion.

    C. Identification of project tasks.

    D. Indicators to eliminate project redundancies.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.