  • Question 451:

    Overlooking negative stakeholders can result in a/an:

    A. decreased likelihood of conflicting interests between stakeholders.

    B. decreased likelihood of the projects progress being impeded

    C. increased likelihood of project failure.

    D. increased likelihood of project success.

  • Question 452:

    Organizational process assets can be divided into which of the following two categories?

    A. Project files and corporate knowledge base

    B. Templates, and processes and procedures

    C. Standards, and processes and procedures

    D. Corporate knowledge base and processes and procedures

  • Question 453:

    PMBOI Guide is a standard that describes:

    A. product-oriented processes.

    B. project management processes.

    C. product-oriented and project management processes.

    D. program management and project management processes.

  • Question 454:

    On what is project baseline development established?

    A. Approved product requirements

    B. Estimated project cost and schedule

    C. Actual project cost and schedule

    D. Revised project cost and schedule

  • Question 455:

    One of the fundamental tenets of modern quality management states that quality is:

    A. planned, designed, and built in.

    B. planned, designed, and inspected in.

    C. built in, created, and reviewed.

    D. built in, created, and standardized.

  • Question 456:

    In which process group is the scope first defined?

    A. Initiating

    B. Planning

    C. Executing

    D. Controlling

  • Question 457:

    Inputs to the Define Activities process include:

    A. Project scope statement, resource calendars, and work performance information.

    B. Scope baseline, enterprise environmental factors, and organizational process assets.

    C. Project scope statement, approved change requests, and WBS dictionary.

    D. Scope baseline, enterprise environmental factors, and activity duration estimates.

  • Question 458:

    A project manager needs to deliver the project 2 weeks before the planned date without changing the scope. Which of the following techniques may be applied to reevaluate the schedule?

    A. What-if scenario analysis

    B. Critical chain method

    C. Schedule crashing

    D. Resource leveling

  • Question 459:

    A risk may be graded into different priorities by which process?

    A. Risk monitoring and controlling

    B. Risk response planning

    C. Qualitative risk analysis

    D. Quantitative risk analysis

  • Question 460:

    Activities on the critical path have which type of float?

    A. Zero free float

    B. Zero or negative float

    C. Negative and positive float

    D. Zero or positive float

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.