In the Initiating Process Group, at what point does the project become officially authorized?
A. When the project charter is signed
B. When all the stakeholders agree on the scope of the project
C. When the project manager is appointed
D. When the necessary finance or funding is obtained
In which of the following types of organizations is resource availability moderate to high?
A. Weak matrix
B. Balanced matrix
C. Strong matrix
D. Projectized
Which of the following is an output of Close Procurements?
A. Accepted deliverables
B. Organizational process assets updates
C. Managing stakeholder expectations
D. Performance reports
The probability and impact matrix is primarily used to:
A. Quantify risk issues for trends during a quality audit.
B. Develop a risk register for risk planning.
C. Evaluate each risk's importance and priority during Perform Qualitative Risk Analysis.
D. Define risk and compare impacts during Perform Quantitative Risk Analysis.
A car company authorized a project to build more fuel-efficient cars in response to gasoline shortages. With which of the following strategic considerations was this project mainly concerned?
A. Market demand
B. Legal requirements
C. Strategic Opportunity
D. Technological advance
A Pareto chart is a specific type of:
A. control chart
B. histogram
C. cause-and-effect diagram
D. scatter diagram
A process is defined as:
A. A set of interrelated actions and activities performed to achieve a certain objective.
B. A set of guidelines that explains how to carry out a particular task.
C. The inputs for a task and the tools and techniques required to carry out the task.
D. A collection of logically related project activities, usually culminating in the completion of a major deliverable.
A project can be defined as a: A. Temporary endeavor undertaken to create a unique product, service, or result
B. Temporary endeavor that produces repetitive outputs
C. Permanent endeavor undertaken to create a unique product, service, or result
D. Permanent endeavor that produces repetitive outputs
At which stage of team development do members begin to work together, adjust work habits, and trust each other?
A. Forming
B. Storming
C. Norming
D. Performing
Which of the following can be used as an input for Define Scope?
A. Product analysis
B. Project charter
C. Scope baseline
D. Project scope statement
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.