  • Question 521:

    A tool and technique used during the Define Scope process is:

    A. facilitated workshops.

    B. observations.

    C. questionnaires and surveys.

    D. group creativity techniques.

  • Question 522:

    Which of the following response strategies are appropriate for negative risks or threats?

    A. Share, Accept, Transfer, or Mitigate

    B. Exploit, Enhance, Share, or Accept

    C. Mitigate, Share, Avoid, or Accept

    D. Avoid, Mitigate, Transfer, or Accept

  • Question 523:

    Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:

    A. manager.

    B. success.

    C. deadline.

    D. scope.

  • Question 524:

    Which of the following is a tool or technique used in the Acquire Project Team process?

    A. Networking

    B. Training

    C. Negotiation

    D. Issue log

  • Question 525:

    Which of the following change requests can bring expected future performance of the project work in line with the project management plan?

    A. Corrective action

    B. Defect repair

    C. Preventative action

    D. Probable action

  • Question 526:

    Which input will be used when tasked with developing the human resource plan?

    A. Project management plan

    B. Activity resource requirements

    C. Resource calendar

    D. Project staff assignments

  • Question 527:

    Which of the following are an enterprise environmental factor that can influence the Identify Risks process?

    A. Work performance reports

    B. Assumptions logs

    C. Network diagrams

    D. Academic studies

  • Question 528:

    Which Control Scope input is compared to actual results to determine if corrective action is required for the project?

    A. Scope baseline

    B. Scope management plan

    C. Change management plan

    D. Cost baseline

  • Question 529:

    Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?

    A. Variance Analysis

    B. Define Scope

    C. Verify Scope

    D. Control Scope

  • Question 530:

    The total of the planned value (PV) is also known as:

    A. work breakdown structure (WBS).

    B. schedule target.

    C. performance measurement baseline (PMB).

    D. earned value baseline.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.