Using the three-point estimating technique, if the most likely duration is four months, the optimistic duration is two months, and the pessimistic duration is one year, how many months is the expected activity duration?
A. Two
B. Four
C. Five
D. Twelve
A project lifecycle is defined as:
A. a collection of generally sequential and sometimes overlapping project phases.
B. a process required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
C. a recognized standard for the project management profession.
D. the application of knowledge, skills, tools, and techniques to project activities to meet the project requirements.
Administer Procurements is part of which Process Group?
A. Planning
B. Executing
C. Monitoring and Controlling
D. Closing
The process to ensure that appropriate quality standards and operational definitions are used is:
A. Plan Quality.
B. Perform Quality Assurance.
C. Perform Quality Control.
D. Total Quality Management.
Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?
A. Initiating
B. Planning
C. Executing
D. Closing
A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?
A. Slack
B. Float
C. Lag
D. Lead
The completion of the project scope is measured against the:
A. requirements documentation.
B. project scope statement.
C. project management plan.
D. work performance measurements.
The diagram below is an example of a:
A. Risk breakdown structure (RBS).
B. Project team.
C. SWOT Analysis.
D. Work breakdown structure (WBS).
Who is responsible for initiating a project?
A. Project sponsor
B. Project manager
C. Program manager
D. Project management office (PMO)
Which type of diagram includes groups of information and shows relationships between factors, causes, and objectives?
A. Affinity
B. Scatter
C. Fishbone
D. Matrix
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.