  • Question 551:

    Activity cost estimates are quantitative assessments of the probable costs required to:

    A. Create WBS.

    B. complete project work.

    C. calculate costs.

    D. Develop Project Management Plan.

  • Question 552:

    The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS:

    A. dictionary.

    B. chart.

    C. report.

    D. register.

  • Question 553:

    How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?

    A. Keep satisfied

    B. Keep informed

    C. Manage closely

    D. Monitor

  • Question 554:

    The project has a current cost performance index of 0.80. Assuming this performance will continue, the new estimate at completion is $1000. What was the original budget at completion for the project?

    A. $800

    B. $1000

    C. $1250

    D. $1800

  • Question 555:

    Who determines which dependencies are mandatory during the Sequence Activities process?

    A. Project manager

    B. External stakeholders

    C. Internal stakeholders

    D. Project team

  • Question 556:

    Risk exists the moment that a project is:

    A. planned.

    B. conceived.

    C. chartered.

    D. executed.

  • Question 557:

    Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?

    A. Cost Plus Award Fee Contract (CPAF)

    B. Firm-Fixed -Price Contract (FFP)

    C. Time and Material Contract (TandM)

    D. Cost Plus Incentive Fee Contract (CPIF)

  • Question 558:

    The process of identifying specific actions to be performed to produce project deliverables is:

    A. Define Activities.

    B. Create WBS.

    C. Define Scope.

    D. Develop Schedule.

  • Question 559:

    What is project management?

    A. A logical grouping of project management inputs, outputs, tools, and techniques

    B. Applying knowledge, skills, tools, and techniques to project activities to meet the project requirements

    C. Launching a process that can result in the authorization of a new project

    D. A formal, approved document that defines how the project is executed, monitored, and controlled

  • Question 560:

    Resource calendars are included in the:

    A. staffing management plan.

    B. work breakdown structure (WBS).

    C. project communications plan.

    D. project charter.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.