Exam Details

  • Exam Code
    :CAPM
  • Exam Name
    :Certified Associate in Project Management (CAPM)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :1470 Q&As
  • Last Updated
    :Apr 19, 2025

PMI PMI Certifications CAPM Questions & Answers

  • Question 701:

    Which activity involves ensuring that the composition of a projects configuration items is correct?

    A. Configuration Identification

    B. Configuration Status Accounting

    C. Configuration Verification and Audit

    D. Configuration Quality Assurance

  • Question 702:

    Which of the following documents allows the project manager to assess risks that may require near term action?

    A. Probability and impact matrix

    B. Contingency analysis report

    C. Risk urgency assessment

    D. Rolling wave plan

  • Question 703:

    In which process is a project manager identified and given the authority to apply resources to project activities?

    A. Acquire Project Team

    B. Develop Project Management Plan

    C. Manage Project Execution

    D. Develop Project Charter

  • Question 704:

    Which of the following tools and techniques is used in the Verify Scope process?

    A. Inspection

    B. Variance analysis

    C. Expert judgment

    D. Decomposition

  • Question 705:

    Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area?

    A. Project Time Management

    B. Project Cost Management

    C. Project Scope Management

    D. Project Human Resource Management

  • Question 706:

    Which is a communication method used in the Report Performance process?

    A. Expert judgment

    B. Project management methodology

    C. Stakeholder analysis

    D. Status review meetings

  • Question 707:

    Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact takes place in which process?

    A. Monitor and Control Risks

    B. Plan Risk Management

    C. Perform Qualitative Risk Analysis

    D. Perform Quantitative Risk Analysis

  • Question 708:

    Which type of analysis is used as a general management technique within the Plan Procurements process?

    A. Risk assessment analysis

    B. Make or buy analysis

    C. Contract value analysis

    D. Cost impact analysis

  • Question 709:

    Which Perform Quality Control tool graphically represents how various elements of a system interrelate?

    A. Control chart

    B. Flowchart

    C. Run chart

    D. Pareto chart

  • Question 710:

    How is the schedule variance calculated using the earned value technique?

    A. EV less AC

    B. AC less PV

    C. EV less PV

    D. AC less EV

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.