Which of the following are used when you use the SAP Document Management System in Project System
to assign document info records? There are 2 correct answers to this question.
Response:
A. WBS elements
B. Activities
C. Milestones
D. Structures
Which type of billing is generally used in plant engineering and construction projects? Please choose the
correct answer.
Response:
A. Periodic billing
B. Project billing
C. Milestone billing
D. Fixed billing
How do you derive the hierarchy of a work breakdown structure from the numbers of their WBS elements?
Please choose the correct answer.
Response:
A. Standard structures
B. Coding masks
C. WBS element fields
D. Operative structures
Response:
A. WBS elements
B. Sales orders
C. Settlement rules
D. Result analysis
You have implemented automatic requirements grouping for projects. Once you check the materials
turbine and fittings you realize that the requirements are grouped for turbine but not for fittings. What might
be the reason? Please choose the correct answer.
Response:
A. The grouping indicator of the top WBS element is set to a single MRP Group.
B. The network is set to no grouping for specific MRP Groups.
C. The MRP Group for fittings is deactivated for grouping.
D. The project definition is set to no project stock.
Which type of network does not allow you to assign materials directly, but only indirectly using a bill of
materials?
Please choose the correct answer.
Response:
A. Operative network
B. Task network
C. Standard network
D. Internal network
Response:
A. In Customizing for the Project System, you must have defined profiles for workforce planning in Resources.
B. Assigned work centers to the internally processed activities.
C. Assigned one or more labor capacity to a work center.
What are the three areas of the project screen? There are 3 correct answers to this question. Response:
A. Structure tree
B. Work area and template area
C. Task list area
D. Work area
Which of the following can promptly identify commitments for a project that are too high and trigger various
actions in response? Please choose the correct answer.
Response:
A. Budget plan
B. Availability control
C. Time horizon
D. Tolerance limit
Which of the following costs are automatically calculated based on the resource requirements identified for activities and operations when using networks and activities? Please choose the correct answer. Response:
A. Actual costs
B. Manual costs
C. Planned costs
D. Element costs
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TPLM22_64 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.