Which indicator do you use to define the characteristics of a WBS element and to specify tasks that are performed by the WBS element when the project is executed? Please choose the correct answer. Response:
A. Cost indicators
B. Project cost indicators
C. Operative indicators
D. Billing indicators
What are the various transactions in SAP PS with which a work breakdown structure can be created?
There are 3 correct answers to this question.
Response:
A. Structure planning
B. Project planning
C. Project planning board
D. Create work breakdown structure
In general the costs of internally processed activities and general cost activities can be distributed as required over the network duration and this distribution is controlled using a distribution key that can be stored in the activity. How are costs distributed if a distribution key is not maintained in the activity for internally processed activities? Please choose the correct answer. Response:
A. The costs are distributed evenly over the earliest dates in the activity
B. The system uses the key from the work center
C. System uses valuation variant
D. Costing key is considered
Based on which of the following the checking control function determines whether an order type will be checked and if so, which checking rules should be used? Please choose the correct answer. Response:
A. Status
B. Scope
C. Group
D. Check indicator
Which of the following type determines which type of orders a system can create during assembly
processing? Please choose the correct answer.
Response:
A. Assembly type
B. Order type
C. Account assignment category
D. Item type
In which transactions can you specify whether networks are scheduled together with maintenance orders
that have been assigned as sub networks? There are 2 correct answers to this question.
Response:
A. Project scheduling
B. Overall network scheduling
C. Network scheduling
D. Forward scheduling
With reference to material requirements in Project System (PS-MAT), which of the following statements
are true?
Please choose the correct answer.
Response:
A. 9999 components may be created per network.
B. Project System supports consignment stock.
C. Component scrap is considered during BOM explosion.
Assume you have created a sales order for a material to which a strategy group for assembly processing
has been assigned and the system automatically created a so-called assembly order in the background
and started assembly processing.
In this case, the assembly processing omits which stage and generates an operative order directly from
the sales order?
Please choose the correct answer.
Response:
A. Billing stage
B. Delivery stage
C. MRP Planning stage
D. Scheduling stage
What is the transaction code for editing the planning profile? Please choose the correct answer. Response:
A. OPSS
B. OPDS
C. OPSB
D. OPSC
Where else should you make manual changes; if you assign bill of materials (BOM) items to a network activity manually by exploding the BOM and then changed the BOM? Please choose the correct answer. Response:
A. Network
B. Assignments
C. Cost object
D. Material view
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TPLM22_64 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.