You are using the billing and down payment processing in Sales and Distribution and updating the actual
data to billing elements in the project system. Which of the following business processes can be mapped
in Sales and Distribution? There are 3 correct answers to this question.
Response:
A. Fixed down payment amounts and fixed milestone billing amounts
B. Fixed down payment amounts and resource-related milestone billing amount
C. Resource-related down payments and milestone billing amount
D. Milestone billing of budgeted WBS elements
E. Milestone billing of statistical WBS elements
Which of the following helps you to adjust cost planning to changing circumstances during the execution
phase of the project?
Please choose the correct answer.
Response:
A. Progress analysis
B. Cost forecasts
C. Overhead costs
D. Interest forecast
In internal processing which views allow you to easily and quickly assign persons to activities and use
various data (availability of the person from Human Resources, the total work planned for that person, or
the activity date)? There are 2 correct answers to this question.
Response:
A. Project view
B. Resource view
C. Work center view
D. Assignment view
What is the flag used for WBS elements for which you want to plan costs? Please choose the correct answer. Response:
A. Planning elements
B. Assignment elements
C. Billing elements
D. Revenue elements
Which of the following determines the item category assigned in the sales documents? There are 2 correct
answers to this question.
Response:
A. Sales document type
B. Schedule line items
C. Material pricing group
D. Material item category group
Your projects consist of WBS elements, several networks, and subnetworks.What are the advantages of
new overall network scheduling (CN24N) instead of the old overall network scheduling (CN24)? There are
3 correct answers to this question.
Response:
A. Scheduling of subnetworks and subordinate internal orders
B. Introduction of a configurable level concept for the targeted selection of
C. Scheduling that takes available capacities and material availability into
D. Improve performance through the targeted selection of subnetworks to be
E. Detailed subnetwork monitor
Which SAP standard item category always leads to direct procurement and a purchase requisition
generated by the network?
Please choose the correct answer.
Response:
A. Non-stock item
B. Stock item
C. Billing item
D. Non-billing item
In which type of settlement the costs of all the periods up to the one you specify in settlement are settled?
Please choose the correct answer.
Response:
A. Periodic settlement
B. Full settlement
C. Profile settlement
D. Overview settlement
Assume a scenario where deviations from the project plan occurred as a result of delivery problems, price fluctuations, and unforeseeable capacity bottlenecks. How do you ensure that claims resulting from deviations are prepared for contractual partners and submitted to them at suitable point of time? Please choose the correct answer. Response:
A. Safety measures
B. Status management
C. Claim management
D. Actions
Which indicator automates the grouping of project stock assigned to individual WBS elements to the top
WBS element?
Please choose the correct answer.
Response:
A. Project stock indicator
B. Requirements indicator
C. Project element indicator
D. Automatic requirement grouping
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TPLM22_64 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.