Which of the following processes incorporates the make-or-buy analysis?
A. Procurement management
B. Risk management
C. Quality management
D. Scope management
A project sponsor has requested that weekly status updates are to be sent by email, detailing the schedule performance index (SPI) and schedule variance (SV) of the project. In which of the following documents should these requirements be included?
A. Communications management plan
B. Cost management plan
C. Project charter
D. Contract management plan
Which of the following are characteristics of a projects critical path? (Select Two).
A. The critical path is the longest duration.
B. The critical path has the least amount of resources.
C. The critical path is the shortest duration.
D. The critical path has less than or equal to zero float time.
E. The critical path has a greater than zero float time.
In a highway project 5 miles (8 kilometers) out of the total 15 miles (24 kilometers) have been completed. The BAC is $900,000. Which of the following represents the EV of this project?
A. $150,000
B. $300,000
C. $450,000
D. $600,000
In a highway project 5 miles (8 kilometers) out of the total 15 miles (24 kilometers) have been completed. The BAC is $900,000. Which of the following represents the ETC of this project?
A. $150,000
B. $300,000
C. $450,000
D. $600,000
An ongoing project has a BAC of $450,000, an EV of $110,000 and an AC of $100,000. Which of the following is the CPI of the project?
A. $340,000
B. 1.1
C. $10,000
D. .91
Which of the following is the correct formula for computing a projects SPI?
A. SPI = EV - AC
B. SPI = EV / PV
C. SPI = EV - PV
D. SPI = EV / AC
Which of the following is the main objective for a work breakdown structure (WBS)?
A. To develop a proven methodology that will assist the project manager with the delegation of authority.
B. To decompose the project down into manageable parts.
C. To develop the estimating and detailed scheme of the project.
D. To build on individual development, independent of the team efforts.
Which of the following are characteristics of an approved project charter? (Select Two).
A. Provides the prioritization of work from the stakeholders.
B. Defines the project managers authority.
C. Identifies what the project manager wants to derive from the project.
D. Increases the number of just-in-time processes required to decrease scope creep.
E. Validates the existence of a project.
Which of the following is the purpose of a milestone schedule?
A. A detailed summary of the project milestones that need to be achieved.
B. A summary level timetable of the major project milestones.
C. A summary of the anticipated milestones and the issues identified for the project.
D. A detailed summary of the anticipated milestones and risks identified for the project.
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your JK0-017 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.