Exam Details

  • Exam Code
    :JK0-017
  • Exam Name
    :CompTIA E2C Project+
  • Certification
    :CompTIA Certifications
  • Vendor
    :CompTIA
  • Total Questions
    :402 Q&As
  • Last Updated
    :Apr 16, 2025

CompTIA CompTIA Certifications JK0-017 Questions & Answers

  • Question 171:

    A project manager learns that a team member has falsified work experience, and does not have the knowledge required to complete the task. Which of the following should the project manager do?

    A. Reassign the individual to another role on the project team.

    B. Ignore the situation hoping that everything works out for the best.

    C. Assign other individuals to assist on the task to ensure the task does not get delayed further.

    D. Replace the member and ask the team manager to assign a more qualified person.

  • Question 172:

    Which of the following is the primary purpose of a project tollgate?

    A. Review the tasks from the next phase of the project.

    B. Review changes to a project.

    C. Get acceptance to move the project to the next phase of work.

    D. Give a status update on a set of deliverables.

  • Question 173:

    Which of the following are schedule compression techniques? (Select Two).

    A. Fast tracking

    B. Critical Path Method (CPM)

    C. Crashing

    D. PERT analysis

    E. Schedule network analysis

  • Question 174:

    The communication plan for a project is a subset of which of the following documents?

    A. Project charter

    B. Risk management plan

    C. Project schedule

    D. Project plan

  • Question 175:

    Whose approval should be obtained before modifying the scope of a project?

    A. Project team

    B. Executive management team

    C. Change control board

    D. Stakeholders

  • Question 176:

    A stakeholder asks the project manager to finish a project early. The project manager should ask the stakeholder to FIRST:

    A. speak to the other stakeholders to get their opinion.

    B. complete a change request form.

    C. speak to the project sponsor.

    D. consider how this might impact the quality of the product.

  • Question 177:

    Which of the following will have the GREATEST impact upon the outcome of a project? (Select Two).

    A. Quality metrics

    B. Scope creep

    C. Performance reports

    D. Project life cycle

    E. Project delays

  • Question 178:

    Which of the following can a project manager use to determine the critical path of a project? (Select Three).

    A. Business requirements

    B. Sequence of activities

    C. Completion date

    D. Stakeholder expectations

    E. Start date

    F. Risk register

  • Question 179:

    Which of the following is an input to a work breakdown structure (WBS)?

    A. Performance reports

    B. Stakeholder analysis

    C. Project scope statement

    D. Variance analysis

  • Question 180:

    Which of the following should be included in a Gantt chart to analyze a project schedule? (Select Three).

    A. Risks

    B. Probability

    C. Cost analysis

    D. Start date

    E. Activity durations

    F. Finish date

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your JK0-017 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.