A project manager is working with a large team on an important project. Many of the team members work remotely. The project manager requires each team member to submit weekly status reports at a certain time each week. One team member consistently submits late status reports. Which of the following should the project manager consider FIRST?
A. Time zones for various work locations
B. Necessity of weekly status reports
C. Format of the status report
D. Past performance reviews of the team member
A team member reports that a system component they are working on causes the system to continually reboot. The project manager should record this in which of the following documents?
A. Quality management plan
B. Communication plan
C. Risk matrix
D. Issue log
A project manager added some experienced team members to work on certain project activities in conjunction with inexperienced team members because the project is behind schedule. Which of the following BEST describes the technique the project manager is using?
A. Schedule optimization
B. Fast tracking
C. Resource management
D. Crashing
A project manager is receiving many requests for changes to a project. Which of the following did the project manager fail to complete?
A. Proper project team selection
B. Subject Matter Expert (SME) solicitation
C. Milestone scheduling
D. Stakeholder analysis
Which of the following skills would be the MOST useful in assembling an effective project team in a functional organization?
A. Compromising
B. Negotiation
C. Estimating
D. Padding
A project manager has been assigned two team members who do not get along. On past projects they have proven very difficult to work with and are often at odds with one another. Which of the following conflict resolution techniques would be BEST to address this?
A. Forcing
B. Avoiding
C. Confronting
D. Compromising
The project has an AC of $5,000. Which of the following would be used to determine the budget needed to complete the project?
A. ETC
B. PV
C. BAC
D. EAC
A project manager has finished the first phase of a project. Who of the following determines if the project continues?
A. End users
B. Project manager
C. Project team
D. Project sponsor
The frequency of measurement would be found in which of the following documents?
A. Risk management plan
B. Scope management plan
C. Quality management plan
D. Communication management plan
The project has been terminated prematurely by the organization. Which of the following will the project manager need to complete?
A. Case study
B. Cost benefit analysis
C. Quality assessment
D. Post-mortem
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your JK0-017 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.