Refer to the attached Exhibit.
Which of the following is the duration of the critical path in the diagram?
A. 2
B. 5
C. 6
D. 7
The change control board approved a request for $25,000 to address rising labor costs of specialized trades. Which of the following documents should be updated?
A. Scope statement
B. Project schedule
C. Resource requirements
D. Project budget
A project manager can create a risk breakdown structure (RBS) to determine which of the following?
A. Risk tolerance
B. Risk probability
C. Risk category
D. Risk impact
The project is behind schedule. A project team member has analyzed the work performance information and has not created the weekly status update because they are uncertain when the update should be completed. Which of the following documents should the team member consult?
A. Communication plan
B. Risk plan
C. Scope plan
D. Quality plan
A project manager has determined the probability and impact of identified project risks. A meeting with the project team will be held to determine how to mitigate risks above the project threshold. Which of the following will be created during this meeting?
A. Risk response strategies
B. Risk register
C. Risk assessment
D. Stakeholder risk tolerance
The change control board has just approved a request to modify the sampling technique for a project. Which of the following documents would the project manager update?
A. Risk management plan
B. Quality management plan
C. Communication management plan
D. Scope management plan
A project manager is comparing their budgeting techniques to the most successful project in the companys history. Which of the following techniques is being utilized?
A. Benchmarking
B. Return on investment
C. Process analysis
D. Cost-benefit analysis
Which of the following would require that the project risk register be updated?
A. A qualitative risk analysis is performed
B. A stakeholder has concerns about material delays
C. The risk management plan is created
D. Increased costs for required materials
Which of the following describes a work breakdown structure (WBS) dictionary?
A. A high level requirements document used to create the WBS.
B. An alphabetical listing of WBS components detailing their associated project schedule dependencies.
C. An organizational reference defining how WBS levels must be decomposed.
D. A supporting document that provides more detail for the WBS components.
Which of the following is a benefit of a work breakdown structure (WBS)?
A. It can determine the amount of progress on the project.
B. It can quickly identify the projects major deliverables and underlying activities with graphical representation.
C. It can quickly identify the probability and impact of project risks.
D. It allows a real time analysis of actual project costs compared to the project baseline to determine the project variances.
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your JK0-017 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.