  • Question 261:

    In pre-project setup, which of the following must be completed prior to validating a project?

    A. Project definition

    B. Preliminary SOW

    C. Project charter

    D. Stakeholder approval

  • Question 262:

    A healthcare company must store project records for seven years. This is an example of which of the following?

    A. Document retention compliance

    B. ISO compliance

    C. Version control compliance

    D. Document version control

  • Question 263:

    Post-mortem analysis occurs in which of the following process groups?

    A. Closing

    B. Pre-project setup

    C. Monitoring / controlling

    D. Planning

  • Question 264:

    Communication preferences, cultural differences, and language barriers are BEST described as which of the following?

    A. Special communication needs of project members

    B. Critical aspects of managing stakeholder expectations

    C. Items within the risk management plan

    D. Reasons for premature project failure / abandonment

  • Question 265:

    Which of the following are components of an internal / external communication plan? (Select Two).

    A. Technology requirements

    B. Communication budget

    C. Distribution list

    D. Stakeholders list

    E. Communication frequency

  • Question 266:

    A project manager creates a detailed list of costs for each activity involved in the project and then uses the sum of the individual activities to create the budget. Which of the following cost estimating techniques was used?

    A. Bottom-up

    B. Expert judgment

    C. Parametric

    D. Top-down

  • Question 267:

    A project manager is responsible for meeting with the companys project review board to periodically evaluate the progress on a project. Which of the following is the role of the board?

    A. To supply audit trail oversight

    B. To ensure local standards compliance

    C. To provide decision oversight

    D. To communicate to stakeholders

  • Question 268:

    A network diagram shows two critical paths for a project. Which of the following will MOST likely increase?

    A. Staff

    B. Risk

    C. Cost

    D. Time

  • Question 269:

    The amount of time ahead or behind schedule on a project is called the:

    A. schedule baseline.

    B. schedule performance index.

    C. estimate to complete.

    D. schedule variance.

  • Question 270:

    A project sponsor is adamant that a complex project must be completed within 12 months. Based on lessons learned from previous projects of this type, the project manager believes that the project cannot possibly finish in less than 24 months. Which of the following tools can the project manager use to show the improbability of the proposed timeline?

    A. Pareto Diagram

    B. Decision tree

    C. Monte Carlo analysis

    D. Quantitative risk analysis

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your JK0-017 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.