A project manager is managing a project that is scheduled to take ten months to complete. The project is in its sixth month and $450,000 has been spent. The project budget is $990,000. Which of the following will the project manager use to determine the budgeted cost of work scheduled?
A. Estimate to completion
B. Planned value
C. Cost performance index
D. Budget at completion
A key stakeholder on a project advises the project manager that there is a component of the project that has yet to be decided. They are concerned that their needs regarding this component will not be addressed. In which of the following documents should the project manager record this information?
A. Lessons learned
B. Issue log
C. Statement of Work (SOW)
D. Project charter
A project manager is new to an organization and is about to begin work on a $1,000,000 project. Which of the following would BEST help the project manager?
A. Reviewing closure reports from previous projects within the organization.
B. Asking stakeholders what standards they consider important.
C. Developing a quality management plan.
D. Talking to other project managers who have been with the organization for a long time.
The project cost performance index is 1.2 and the project manager has spent $71,248 dollars to date. The project is currently 50 percent complete. Which of the following is the earned value (EV)?
A. $35,624.00
B. $59,373.33
C. $71,248.00
D. $85,497.60
The project manager needs to determine the relationship between two variables. Which of the following tools will the project manager use?
A. Histogram
B. Run chart
C. Pareto chart
D. Scatter diagram
Control limits would be found in which of the following plans?
A. Procurement management plan
B. Quality management plan
C. Change management plan
D. Scope management plan
Which of the following activities would happen FIRST in procurement management?
A. Request seller responses.
B. Perform a make or buy analysis.
C. Perform contract administration.
D. Perform vendor selection.
A project manager needs to identify uncertain events during the planning phase. Which of the following documents would be the BEST source of this information?
A. Quality log
B. Risk register
C. Issues log
D. Responsibility assignment matrix
The project manager has been informed that the project team cannot procure any more materials until a new purchase order has been received. The project manager should record this information in which of the following documents?
A. Risk response plan
B. Communications plan
C. Issues log
D. Change control log
A project manager is performing activity sequencing. The project manager is only using start to finish dependencies. Dummy activities are being utilized to define all logical relationships. Which of the following methods is the project manager demonstrating?
A. Precedence Diagramming Method (PDM)
B. Critical Chain Method (CCM)
C. Arrow Diagramming Method (ADM)
D. Critical Path Method (CPM)
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your JK0-017 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.