  • Question 51:

    A qualitative analysis identified a server crash as an internal project risk with a medium probability and high adverse impact to the project. The project manager decides to manage this risk by authorizing the purchase and installation of a tape backup unit for the server, to prevent the potential loss of documents. Which of the following risk response strategies was applied in this circumstance?

    A. Acceptance

    B. Transfer

    C. Mitigation

    D. Avoidance

  • Question 52:

    A project manager decides to manage the threat of a particular risk through the purchase of an insurance policy. Which of the following risk response strategies is being applied?

    A. Avoidance

    B. Transfer

    C. Acceptance

    D. Mitigation

  • Question 53:

    During execution, a project manager of a construction project requires certain project team members to work outdoors, atop tall buildings. Which of the following would BEST mitigate the risk of injury to those team members, without affecting the approved project schedule?

    A. Ensure that project team members do not work in very windy weather.

    B. Ensure that project team members are furnished with slip-resistant boots.

    C. Ensure that project team members are trained in injury response.

    D. Ensure that project team members are covered by applicable insurance.

  • Question 54:

    Several stakeholders and the project sponsor have indicated that they are not being supplied with project

    updates. As the project manager, which of the following should be done to address the situation?

    A. Create a communication roles template.

    B. Speak in-depth personally to each stakeholder.

    C. Send emails to everyone on the project team.

    D. Refer to the communications plan.

  • Question 55:

    Which of the following is used in quality control?

    A. Pareto chart

    B. RACI matrix

    C. PERT

    D. Issues log

  • Question 56:

    To ensure the quality of implemented project change requests, which of the following will need to occur? (Select Two).

    A. The project team is not notified of the approved change.

    B. Change is tracked and is either accepted or rejected by the change control board.

    C. Change is logged and updated in the change log document.

    D. Once a change is forwarded to the change control board, it will be removed from the change log.

    E. Once the change is submitted to the change control board, it will be approved and placed into production.

  • Question 57:

    Pareto charts helps the project manager with which of the following?

    A. Determine if a process will be experiencing difficulties.

    B. Focus on creative thinking.

    C. Explore required future events.

    D. Focus on the most critical issues to improve quality.

  • Question 58:

    Work must be overlapped and completed in parallel rather than sequentially within the critical path in order to meet the end date of the project. Which of the following would be utilized?

    A. Optimizing

    B. Crashing

    C. Resource leveling

    D. Fast-tracking

  • Question 59:

    Which of the following is included within the RFP?

    A. Identify the price quote and include the communication plan.

    B. Request a price and the names of the project resources.

    C. The vendor that will complete the work and the vendors background, history and experience.

    D. Request total cost for all work to be completed and procedures for replying to the bid.

  • Question 60:

    Which of the following is a characteristic of a project charter?

    A. Issued by the project manager with support from the project sponsor.

    B. Links the project to the on-going work of the organization through a business plan.

    C. Formally recognizes the existence or establishment of the project.

    D. Provides low-level requirements for the project.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your JK0-017 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.