All of the following should be detailed in the communications management plan EXCEPT:
A. the person responsible for communicating the information.
B. team member roles and responsibilities.
C. team members that will receive the information.
D. frequency of project team communications.
A project team is comprised of team members based in North America, Europe, the Middle East and the Far East. Which of the following is the MOST efficient means of reporting project updates to all team members?
A. E-mail to all team members
B. A daily web conference
C. A weekly conference call
D. Face to face meeting at a central location
Which of the following describes a qualitative risk analysis tool that assigns ratings to project risk factors based upon the likelihood of occurrence and the affect it will have on the project?
A. Cause and effect diagram
B. Risk register
C. Probability and impact matrix
D. Decision tree analysis
Which of the following would be considered a valid strategy in response to an adverse risk?
A. Exploit
B. Monitor
C. Mitigate
D. Enhance
Which of the following is a quantitative risk analysis tool or technique?
A. Risk register
B. Decision tree analysis
C. Probability and impact matrix
D. Cause and effect diagram
An ongoing project requires several parts manufactured at an outside vendor. If the vendor has sufficient quantity and can still ship today, the parts should be received in five days; although in most cases an order of this size requires ten days. Allowing for an upcoming holiday and some potential bad weather the shipment could take up to twenty-one days. Using the PERT method, which of the following is the correct time estimate for a parts delivery?
A. 10 days
B. 11 days
C. 21 days
D. 36 days
Which of the following is a representation of the amount of money spent on project work at a point in time?
A. CV
B. CPI
C. EV
D. AC
Which of the following is a representation of the difference between the planned costs of work completed compared to the actual cost at a point in time?
A. EV
B. CPI
C. CV
D. AC
A project is cancelled unexpectedly prior to completion. Which of the following would the project manager use to document the details of the project closure?
A. Histogram
B. Post mortem
C. SWOT analysis
D. Project scope statement
Which of the following is the correct progression of the project life cycle?
A. Planning, initiating, executing, monitoring / controlling, closing
B. Initiating, planning, executing, monitoring / controlling, closing
C. Planning, initiating, monitoring / controlling, executing, closing
D. Initiating, planning, monitoring / controlling, executing, closing
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your JK0-017 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.