  • Question 191:

    A project team is ready to identify activities needed to accomplish the project. Which of the following needs to occur FIRST?

    A. PERT

    B. RBS

    C. WBS

    D. OBS

  • Question 192:

    The MOST detailed component of the WBS is known as:

    A. An activity

    B. A cost account

    C. A sub-phase

    D. A work package

  • Question 193:

    Which of the following is the FIRST step in a proper change management procedure?

    A. Coordinate with appropriate stakeholders

    B. Update the project plan

    C. Perform impact analysis

    D. Identify a change

  • Question 194:

    A stakeholder wants to add another requirement to the deliverable. Which of the following will the project manager do to determine the change's effect on the project?

    A. Performing an impact analysis

    B. Identifying a change

    C. Coordinating with stakeholders to select the course of action

    D. Filling out a change control

  • Question 195:

    A change request has been identified and submitted to the Change Control Board for approval. After gaining approval, which of the following should occur NEXT?

    A. Document using the appropriate change control forms

    B. Update the project plan components

    C. Request a meeting with the project sponsor

    D. Perform impact analysis

  • Question 196:

    When dealing with indirect project team members, it is important to recognize which of the following?

    A. Differences of efficiency

    B. Motivation to be engaged on a project

    C. Communication preferences

    D. Functional or hierarchical barriers

  • Question 197:

    Which of the following circumstances could lead to initiating administrative closure?

    A. Project cancellation

    B. Resource constraints

    C. Contract closure

    D. Changes in the critical path

  • Question 198:

    When dealing with remote project team members, it is important to recognize their needs in terms of which of the following? (Select TWO).

    A. Time zone differences

    B. Programming language differences

    C. Cultural differences

    D. Project management differences

    E. Compensation differences

  • Question 199:

    A project manager is involved with minimizing unauthorized changes to the project. Which of the following will BEST assist with these changes?

    A. Risk register

    B. Quality management metrics

    C. Scope statement

    D. Budget scope

  • Question 200:

    Which of the following may include meetings, status reports, and email distribution lists?

    A. Change control plan

    B. Meeting minutes

    C. Project schedule

    D. Communication plan

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-003 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.