  • Question 201:

    A project team has determined that all status reports will be sent via email. Which of the following components of the project plan documents this information?

    A. Status report plan

    B. Communication plan

    C. Discussion plan

    D. Decision log

  • Question 202:

    A project manager is reviewing the scope statement of a project. Which of the following project management plan components would define the measureable tasks of the project?

    A. Issues log

    B. Quality metrics

    C. Resource requirements

    D. Project schedule

  • Question 203:

    Which of the following conflict resolution techniques involves one party overpowering another without regard to relationships within the group?

    A. Avoiding

    B. Smoothing

    C. Forcing

    D. Compromising

  • Question 204:

    Which of the following project documents lists risks and describes the strategy to deal with a risk?

    A. Risk categorization

    B. Risk register

    C. Risk analysis

    D. Risk breakdown structure

  • Question 205:

    Resources for a project report to a project manager and a functional manager. The organizational structure is:

    A. Matrix

    B. Ad hoc

    C. Functional

    D. Projectized

  • Question 206:

    Which of the following conflict resolution techniques focuses on a positive relationship and deemphasizes the area of conflict?

    A. Avoiding

    B. Smoothing

    C. Compromising

    D. Forcing

  • Question 207:

    Which of the following techniques modifies the schedule based upon resource constraints?

    A. Critical Chain Method

    B. Critical Path Method

    C. Arrow Diagramming Method

    D. Precedence Diagramming Method

  • Question 208:

    Which of the following tools would a project manager use to determine the root cause of an issue?

    A. Pareto Chart

    B. Ishikawa Diagram

    C. Histogram

    D. Monte Carlo Analysis

  • Question 209:

    Which of the following activity sequencing techniques uses nodes to symbolize activities and arrows to show how their dependencies are connected?

    A. Critical Path Method

    B. Arrow Diagramming Method

    C. Critical Chain Method

    D. Precedence Diagramming Method

  • Question 210:

    Which of the following activity sequencing techniques uses nodes to symbolize the dependencies of each activity?

    A. Critical Path Method

    B. Critical Chain Method

    C. Arrow Diagramming Method

    D. Gantt Chart Method

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-003 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.