  • Question 601:

    Empirical process control constitutes a continuous cycle of inspecting the process for correct operation and results and adapting the process as needed. What characteristics does this apply to in Scrum?

    A. Self-organization, Collaboration and Time-boxing

    B. Quality, Cost and Scope

    C. Scrums, Sprint and Releases

    D. Transparency, Inspection and Adaption

  • Question 602:

    Bugs reported by the customer that have slipped by all software quality processes are represented in this metric.

    A. Technical debt

    B. Escaped defects

    C. Risk burndown

    D. Code quality

  • Question 603:

    Testing that often occurs between "Done" and "Done, Done" is:

    A. Exploratory testing

    B. Acceptance testing

    C. Unit testing

    D. Test driven development

  • Question 604:

    Which of the following is NOT one of the 12 core practices of XP:

    A. The Planning Game

    B. Planning Poker

    C. Small Releases

    D. System Metaphor

  • Question 605:

    Which of the following is NOT one of the 12 core practices of XP:

    A. Pair Programming

    B. Collective Code Ownership

    C. 40-Hour Work Week

    D. Minimize Waste

  • Question 606:

    Which of the following is NOT one of the 12 core practices of XP:

    A. Simple Design

    B. Continuous Testing

    C. Vertical Slicing

    D. Refactoring

  • Question 607:

    Which of the following is NOT one of the 12 core practices of XP?

    A. Visualize the flow

    B. On-site Customer

    C. Coding Standards

    D. System Metaphor

  • Question 608:

    Which of the following is NOT a reason to use a Feature Breakdown Structure (FBS) instead of a Work Breakdown Structure (WBS)?

    A. It allows communication between the customer and the development team in terms both can understand.

    B. It allows you to baseline your project plan due to absence of change.

    C. It allows tracking of work against the actual business value produced.

    D. It allows the customer to prioritize the team's work based on business value.

  • Question 609:

    Team members who are part-time on your project will see at least a 15% reduction in their productivity per hour. The type of resource model in Agile is called:

    A. Collocated

    B. Fractional assignments

    C. Distributed resources

    D. Over-allocated resources

  • Question 610:

    Frequent verification and validation is key in Agile but each approach produces a very different result. Verification determines ________________ whereas validation determines _____________.

    A. if the product is "done" | if the product is "done-done"

    B. if I am I building the product right | if I am I building the right product

    C. if I am I building the right product | if I am I building the product right

    D. if the product has passed unit testing | if the product has passed acceptance testing

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-ACP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.