Based on the following information, determine the number weeks until the next release.
A. 8 weeks
B. 12 weeks
C. 16 weeks
D. 9 weeks
Which of the following is an example of an information radiator?
A. An email of a status report
B. A text of a quick question to the Product Owner
C. A whiteboard showing the state of work
D. A face-to-face conversation
What type of time estimation excludes non-programming time?
A. Ideal Time
B. Calendar time
C. Duration
D. Real Time
Assuming all projects require the same amount of up-front investment, the project with the highest ______________ would be considered the best and undertaken first.
A. Earned Value Management (EVM)
B. Internal Rate of Return (IRR)
C. Net Present Value (NPV)
D. Budget at Completion (BAC)
80% of the value comes from 20% of the work. Which law is this referring to?
A. Parkinson's Law
B. Moore's Law
C. Pareto's Law
D. Jevon's Paradox
Match the story types on the left to their definition on the right:
Select and Place:
Match the traditional contract model of the left with the Agile alternative on the right.
Select and Place:
Sequence the steps to User Story Mapping.
Select and Place:
Match the following roles on the right to the RASCI on the left:
Select and Place:
Order the 5 focusing steps of the Theory of Constraints.
Select and Place:
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-ACP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.