Which technique is used by a project team to estimate the amount of work that can be done per iteration?
A. Velocity measurement
B. Relative prioritization
C. Planning Poker
D. Release planning
During which activity is the sequence of numbers 0, 1, 2, 3, 5, 8, 13 often used?
A. Denoting development sequence
B. Estimating development hours
C. Indicating priority of a story
D. Estimating points of a story
Scrum practices are facilitated by the:
A. ScrumMaster.
B. Product Owner.
C. Project Sponsor.
D. Scrum team.
The process of reviewing, testing, and accepting implemented features is called:
A. Retrospective.
B. Stakeholder review.
C. Scope verification.
D. Iteration planning.
Retrospectives provide an opportunity for the team to:
A. Reflect at the end of every iteration and identify improvements that will increase the quality of the product.
B. Participate in a mandatory meeting to share status updates across the team and to ensure that everyone is on track.
C. Understand from the management if the project is achieving the Scope, Quality, Cost, and Schedule goals.
D. Set goals at the beginning of the iteration and identify requirements that can be delivered in that iteration.
In Agile projects, how are planning outputs shared with stakeholders?
A. Using the most highly visible method possible
B. On a need-to-know basis depending on role
C. According to the project communications plan
D. Through a series of stakeholder meetings
Which of the following is critical for the success of distributed Agile teams?
A. Cost containment
B. High volume of communication
C. Shared knowledge
D. Culture of collaboration
The three questions asked at every Daily Scrum should be: "What have you accomplished since the last Daily Scrum?";"What are you planning to accomplish between now and the next Daily Scrum?"; and:
A. What is preventing you from completing your work effectively?
B. What is yourcurrent performance velocity?
C. Are you on track to complete assigned story points?
D. How many story pointswill you complete this sprint?
Which of the following is most appropriate to always participate in Planning Poker?
A. Product Owner
B. Stakeholders
C. Team members
D. Project manager
How does Empirical Process Control support Agile methodologies?
A. Testing, requirements, and adaptation
B. Testing, requirements, and change
C. Visibility, review, and testing
D. Visibility, inspection, and adaptation
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-ACP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.