Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Mar 29, 2025

PMI PMI Certifications PMI-SP Questions & Answers

  • Question 81:

    If you are the project manager of the BNQ Project and you add "waiting time" between two activities, then what have you added in the project?

    A. You have added lag time to the project activities.

    B. You have added management reserve to the project activities.

    C. You have added lead time to the project activities.

    D. You have added float to the project activities.

  • Question 82:

    You are the project manager of the NHQ Project. You are coaching Alice, a new project manager, on the relationships in a project network diagram. Which relationship type between activities are the most common?

    A. SS

    B. FS

    C. FF

    D. SF

  • Question 83:

    Complete this sentence:

    _________________________ is the process of collecting and distributing performance information including status reports, progress measurements, and forecasts.

    A. Corrective action

    B. Report performance

    C. Earned value management

    D. Monitor and control project performance

  • Question 84:

    Your organization wants to start a new project. The study shows that the new project will save organization approximately $200,000 per year. Now it is required to move forward with the project. Which of the following documents will define the project justification?

    A. Feasibility study

    B. Project charter

    C. Work breakdown structure

    D. Project scope

  • Question 85:

    You are the project manager for your organization. You have worked with the project team to create the project scope statement. The key stakeholders have signed off on the project scope and they are eager for you and the project team to begin creating the deliverables identified within the project scope. What process must you and the project team complete next in this scenario?

    A. Create the activity list.

    B. Create the WBS.

    C. Create the risk assessment.

    D. Determine the project budget.

  • Question 86:

    John is a scheduler in ABC Company. He has to plan an activity for the schedule models. Which of the following activities will he use to make the schedule models? . Each correct answer represents a complete solution. Choose all that apply.

    A. Hammocks

    B. Critical path scheduling

    C. Flags

    D. Tasks

  • Question 87:

    Holly is the project manager for her organization. Her current project is running late and her project customer has asked Holly to find a method to apply corrective actions to the project schedule. Holly is exploring the concept of crashing the project. Which of the following statements is true about crashing the activities in Holly's project?

    A. The activities to be crashed must have additional quality control metrics associated with them.

    B. The activities to be crashed cannot be of fixed duration.

    C. The activities to be crashed cannot have risks associated with them greater than 0.80.

    D. The activities cannot be on the critical path in order to be crashed.

  • Question 88:

    Yolanda is the project manager for her organization. She is creating a performance report for her sponsor. Typically, the performance report includes all of the following factors except for which one?

    A. Current status of risk and issues

    B. Quality control activities

    C. Analysis of past performance

    D. Work to be completed next

  • Question 89:

    John works as a project manager for BlueWell Inc. His project has a budget of $795,000 and he has spent $325,000 on the project. But, he has completed only 40 percent of the project work till now. Management wants to know what the project's cost performance index is. What value will John report?

    A. 0.76

    B. 0.85

    C. 0.80

    D. 0.92

  • Question 90:

    You are the project manager of the NGG Project. This project will be using a new material that the project team has never worked with before. You'd like to use some preventive action to ensure that the installation of the new materials is successful in the project. Which one of the following project actions is an example of the best preventive action for this project?

    A. Hire a subject matter expert to train the project team how to install the materials.

    B. Purchase additional materials so in case the team wastes materials during their installation.

    C. Hire a subject matter expert to install the new materials.

    D. Create incentive by rewarding the project team if they don't waste the materials.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.