Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Apr 16, 2025

PMI PMI Certifications PMI-SP Questions & Answers

  • Question 181:

    You work as a project manager for BlueWell Inc. You are calculating the performance indexes of your project. The cost variance (CV) of your project is 30. What does this figure depict?

    A. Project is behind the schedule.

    B. Costs are higher than planned.

    C. Costs are right on target.

    D. Costs are lower than planned.

  • Question 182:

    Vicky is the project sponsor of Robert's project. She has requested several changes for the project scope and these changes have, of course, been approved. Robert needs to incorporate the project scope changes into the activity list. Where else should Robert reflect these project changes?

    A. Project final report

    B. Scope baseline

    C. Quality control mechanism

    D. Cost baseline

  • Question 183:

    You are the project manager for your organization. Your project will need four electrical engineers for the project though there are no electrical engineers within your department. This scenario is best described as which one of the following terms?

    A. Assumption

    B. Risk

    C. Resource requirement

    D. Resource constraint

  • Question 184:

    Bonnie is the project manager for her organization. She is developing a strategy to manage the project stakeholders. She wants to identify the key stakeholders, their influence over the project, their interest in project, and an assessment of methods. What can Bonnie create to gain support from the stakeholders in her project?

    A. Stakeholder identification tools

    B. Expert judgment

    C. Stakeholder Analysis Matrix

    D. Communications management plan

  • Question 185:

    You work as a project manager for BlueWell Inc. Which of the following plans will you use to define how resources are brought onto the project team, how they are managed while on the project team, and how they may be released from the project team?

    A. Project Schedule Management Plan

    B. Project Staffing Management Plan

    C. Project Human Resources Management Plan

    D. Project Communications Management Plan

  • Question 186:

    Wendy is the project manager for the NHQ project. She is working with her project to begin creating the project duration estimate. Her organization is in weak matrix and several of the project team members are scheduled to complete work on other projects. What input will most likely be of the biggest assistance as Wendy and the project team begin creating the duration estimate for this project?

    A. Project charter

    B. Project scope statement

    C. Project communications management plan

    D. Resource calendar

  • Question 187:

    Billy is the project manager of the PQW Project and she has an assigned project budget of $655,000. Currently she is 80 percent complete with the project though she was scheduled to be 90 percent done by this date. She has spent $490,000 to date. What should Billy report as her cost performance index (CPI)for this project?

    A. .07

    B. 1.07

    C. $34,000

    D. .89

  • Question 188:

    Beth works as a project manager for BlueWell Inc. Which of the following tools and techniques of Administer Procurements process will Beth use to manage contracts, and procurement documentation and records?

    A. Records Management System

    B. Performance reporting

    C. Inspection and Audit

    D. Payment System

  • Question 189:

    You work as a project manager for BlueWell Inc. Management has asked you to communicate with them whenever your project is about to reach a milestone so that they can review your project performance to date. Where can you find a list of the project milestones to anticipate management's request?

    A. Scope baseline

    B. Milestone list

    C. Project charter

    D. Project Schedule Management Plan

  • Question 190:

    You are the project manager of the NHQ project. You are working with your project team to create the project schedule and the project network diagram. In order to start the sequencing of the project activities, you will need a document to identify the result of project phases, key project deliverables, and significant, timeless events in the project. Which of the following documents will you need to help sequence the project work?

    A. Activity attributes

    B. Activity list

    C. Project scope statement

    D. Milestone list

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.