Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Apr 16, 2025

PMI PMI Certifications PMI-SP Questions & Answers

  • Question 171:

    You are working with your project team to control the project schedule. You will need five inputs to this process throughout your project. Which one of the following is an output of the project schedule control, and NOT an input?

    A. Work performance information

    B. Project schedule

    C. Project management plan

    D. Work performance measurements

  • Question 172:

    You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone, which accounts for half of the project completion. There have been some errors in the project, which has caused you to spend $2,073,654. Based on the budget at completion, what is this project's to-complete performance index?

    A. -$108,120

    B. 0.98

    C. $2,500.000

    D. 1.02

  • Question 173:

    You are the project manager of the OOI Project and you're forty percent complete with this project. The project has a BAC of $2,345,650 and you have spent $950,000 to date. Based on your aggressive scheduling you should be at the 45 percent milestone today, but due to some early delays you're running late. What is the planned value of your project?

    A. $950,000

    B. $2,375,000

    C. $1,055,543

    D. $938,260

  • Question 174:

    You are the project manager of the NDF project. You need to determine how often a complete project report can be made, including forecasted project completion information for your project. How often should the report be created?

    A. Weekly

    B. One per status milestone reached

    C. Regularly or on an exception basis

    D. Exception-by-exception basis

  • Question 175:

    You are the project manager for your organization. You and the project team are developing the project schedule for your current project. This project management process will create four outputs. Which of the following is an output of the Develop Schedule process?

    A. Work performance information

    B. Schedule baseline

    C. Resource calendars

    D. Activity duration estimates

  • Question 176:

    Nancy is the project manager of a project with 78 stakeholders. This is a high-profile project and she needs to express to her project team and to the management the importance of communication in this project. She would like to show the number of stakeholder communication channels in the project. Based on this information how many communication channels exist within this project?

    A. 78

    B. 156

    C. 3,003

    D. 6,084

  • Question 177:

    In the project time management knowledge area, there are six processes. According to the PMBOK, which project time knowledge area will have the majority of the effort?

    A. Estimate activity resources

    B. Define activities

    C. Control schedule

    D. Develop schedule

  • Question 178:

    You are the project manager for your organization. Management has offered you a bonus if you can complete the project work two months earlier than what your schedule predicts. You can use a schedule compression technique, but management does not want to increase costs in the project. What approach would you recommend to condense the project duration?

    A. Fast tracking

    B. Crashing

    C. Effort-driven activity analysis

    D. Rewards and recognition for the project team

  • Question 179:

    You are the project manager of the GHQ Project. You have to prioritize activities for the effective management of project. For this, you have created a network diagram to schedule a set of project activities as shown in the figure:

    Based on this figure, what is the critical path of this project?

    A. ABEHJ

    B. ACFIJ

    C. ADGJ

    D. ACFGJ

  • Question 180:

    You are the project manager for your organization. You are working with your project team to define the project network diagram. Several of the activities in the project schedule appear to have external constraints. Who among the following determines which dependencies are external to the project?

    A. Project team

    B. Project sponsor

    C. Project manager

    D. Project management team

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.