Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Apr 16, 2025

PMI PMI Certifications PMI-SP Questions & Answers

  • Question 211:

    Jack works as a project manager for the NHQ project. His project has a budget of $2,208,456 and is scheduled to last for three years. His project is currently forty percent complete though it should be forty- five percent complete. In order to reach this point of the project, he has spent $725,000. Management needs a performance report regarding the NHQ project. Management is concerned that this project will be over budget upon completion. Management would like to create a report telling them how much more the project will need to complete. What value should Jack tell the management?

    A. $1,087,497.74

    B. $755,000.56

    C. $1,112,978.45

    D. $790,988.76

  • Question 212:

    Which of the group creativity techniques enhances brainstorming with a voting process used to rank the most useful ideas for further brainstorming or prioritization?

    A. Idea/mind mapping

    B. Delphi technique

    C. Nominal group technique

    D. Affinity diagram

  • Question 213:

    Fredrick works as a Project Manager for BlueWell Inc. A number of projects are running under his guidance. You, a team leader of a project, inform Fredrick about the performance indexes of your project. The schedule performance index (SPI) of your project is 1.325. What does this figure indicate?

    A. The schedule performance is better than expected.

    B. The schedule performance is right on target.

    C. The cost performance is better than expected.

    D. The schedule performance is below expectation.

  • Question 214:

    Which of the following statements best describes an activity in a project?

    A. It is a defined set of functions a resource must complete for the project scope to be considered complete.

    B. It is the effort needed to complete a work package.

    C. It is the unit of resource utilization needed to complete a project deliverable.

    D. It is a listing of all project work that must be accomplished for the project scope to be considered complete.

  • Question 215:

    You are working as a project manager for BlueWell Inc. Which of the following tools and techniques of the Define Activity process will help you in identifying the typical schedule milestones?

    A. Expert Judgment

    B. Decomposition

    C. Rolling Wave Planning

    D. Templates

  • Question 216:

    You are a project manager in a matrix environment and management is concerned about the utilization of the resources on your project team and when you'll release them. What project management plan will guide how and when project resources will be released from the project team?

    A. Project Human Resources Management Plan

    B. Project Staffing Management Plan

    C. Project Communications Management Plan

    D. Project Schedule Management Plan

  • Question 217:

    Gary is the project manager of the NHF project, which is a part of a program in his organization. According to the PMBOK, how will Gary provide feedback to programs and portfolios?

    A. Status meetings

    B. Push communications

    C. Regular communications

    D. Status reports and change requests

  • Question 218:

    You are the project manager for your organization. You are working with your project team to create activity duration estimates using the PERT method. What is the formula for PERT?

    A. (O+ML+P)

    B. (O+(6M)+P)6

    C. (O+ML+P)/3

    D. (O+(4M)+P)/6

  • Question 219:

    You are the project manager of the NHQ Project. You have created the project network diagram as shown in the figure:

    Based on the project network diagram, how much float is available for Activity H if Activity B is delayed by four days and Activity D is delayed by two days?

    A. One

    B. Five

    C. Four

    D. Zero

  • Question 220:

    You are the project manager for the NHQ Project. Management has asked you to create a time estimate for this project although you have only just received the project charter. They would like some idea of how long the project will take based on the information in the project charter. While you are uncomfortable giving any type of estimate at this point, you work with your assigned project to create a quick time estimate. What type of estimate have you created for management?

    A. Analogous estimate

    B. Broad estimate

    C. Rough order of magnitude

    D. Expert judgment

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.