Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Apr 07, 2025

PMI PMI Certifications PMI-SP Questions & Answers

  • Question 221:

    You are the project manager of the JKM Project for your organization. Your project is supposed to be 60 percent complete but you are only 45 percent complete. The project has an assigned budget of $765,000 but you have already spent $365,000 to reach this point in the project due to some errors and rework. Management is pressing you on when you'll complete the project and how much the project will likely cost based on the current performance. You need to tell management what the project's current cost performance index (CPI) is. What value should you report to management based on your project's performance?

    A. $306,000

    B. .94

    C. $344,250

    D. .75

  • Question 222:

    Holly is the project manager of the NDS project and she is 85 percent complete with her project though she should be 95 percent complete. Her project has a BAC of $9,850,400 and she has spent $8,011,221 to date. What is Holly's schedule performance index for this project?

    A. 1.07

    B. 0.98

    C. 0.89

    D. Ten percent

  • Question 223:

    You are the project manager for your organization. You are meeting with your customers to discuss the project performance. In this meeting, you will have eight project customers, the project sponsor, and ten members of your project team. What type of communication method are you using in this instance?

    A. Interactive communication

    B. Active communication

    C. Pull technique

    D. Push technique

  • Question 224:

    Which of the following components of the change control system includes the documentation, tracking systems, and defined approval levels necessary for authorizing and controlling changes?

    A. Scope Verification

    B. Configuration Management System

    C. Project Management Information System

    D. Integrated Change Control

  • Question 225:

    Tom is the project manager of the GHQ Project for his organization. He is working on recovering the project schedule. As Tom examines his schedule he is especially aware of project activities with soft logic. What is soft logic?

    A. Soft logic describes activities that do not have particular resources assigned to them.

    B. Soft logic describes activities that can be completed in any order.

    C. Soft logic describes activities that can have lead time added to them.

    D. Soft logic describes activities that can be crashed because they are effort-driven.

  • Question 226:

    You work as a project manager for BlueWell Inc. Your project is falling behind though the project team reports that the actual durations of their work is what they estimated. You investigate the cause and determine that the project team is not starting their assignments early enough to finish their work on time. While the duration of the assignments may be in synchronization with the duration estimates, the completion time is causing the project schedule to slip from the baseline. What can you do to rectify this problem?

    A. Increase the duration estimates for each activity.

    B. Discipline the project team.

    C. Add management reserve.

    D. Corrective actions.

  • Question 227:

    You work as a project manager for BlueWell Inc. You want to increase the overall duration of the project. If the management elects to use resource leveling, then what will happen to the project duration?

    A. The duration will increase, but the labor will stay the same.

    B. The duration will decrease as new team members are brought onto the project.

    C. Nothing, new resources will be incorporated into the project team.

    D. The duration will increase, but the labor will decrease.

  • Question 228:

    Management is concerned about your project. They want to know how the project is performing specifically the schedule performance index. What formula do you use to find the schedule performance index?

    A. PV/EV

    B. EV-AC

    C. EV-PV

    D. EV/PV

  • Question 229:

    You are the project manager for your organization. Management has asked you to document the holidays, weekends, and other corporate working hours, which will supersede the project timings for your schedule. Which calendar will communicate to the project stakeholders, when the project work will take place within the organization?

    A. Project calendar

    B. Resource calendar

    C. Organizational calendar

    D. Company calendar

  • Question 230:

    Tom works as the project manager for BlueWell Inc. He is working with his project to ensure timely and appropriate generation, retrieval, distribution, collection, storage, and ultimate disposition of project information. What is the process in which Tom is working?

    A. Work performance measurement

    B. Stakeholder expectation management

    C. Project communication management

    D. Stakeholder analysis

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.