Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Apr 16, 2025

PMI PMI Certifications PMI-SP Questions & Answers

  • Question 201:

    Lara has been assigned to a construction project. The project includes constructing a residential building with fifty flats. On which of the following events will the project be considered successful?

    A. The project meets or exceeds the expectations of the stakeholders.

    B. The building is complete and handed over to the authority concerned.

    C. The keys of the first flat are handed over to the owner of the flat.

    D. Successful possession of all flats is made.

  • Question 202:

    You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned and they'd like to know what is your schedule performance index. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450, what is the SPI for this project?

    A. $227,140

    B. 0.75

    C. 0.95

    D. -$56,789

  • Question 203:

    Examine the figure given below.

    In this project network diagram, what is the total float for Activity I?

    A. Three

    B. Zero

    C. Five

    D. One

  • Question 204:

    You are the project manager of the SWC project. You have created the stakeholder register. In the stakeholder register of your project, you will have all of the following information except for which one?

    A. Stakeholder classification

    B. Project management team's classification

    C. Assessment information

    D. Identification information

  • Question 205:

    Thomas works as a contract-based project manager for BlueWell Inc. Management has hired Thomas to manage a high-risk project because Thomas has years of experience with this technology and similar project. Thomas would like to use his own templates for the project schedule, quality, and risk management approach. Management is fine with this, except after reviewing the template they had preferred Thomas to use 24-hour time periods for his project calendar rather than the 8-hour time periods as indicated. Thomas agrees, but now he has to update what document in his project management plan?

    A. Project calendar

    B. Activity attributes

    C. Resource calendar

    D. Schedule management plan

  • Question 206:

    You work as a project manager for BlueWell Inc. You are in the process of identifying all the people and organization impacted by the project. Mark, a project team member, has some doubts about the inputs of the Identify Stakeholder process. What is referred to as an input to the identify stakeholder process in project communication management?

    A. Expert judgment

    B. Project charter

    C. Stakeholder analysis

    D. Stakeholder register

  • Question 207:

    You are the project manager for your organization. You are working on creating the activity list so that you can create the project schedule. This current project is similar to a project you have completed for your company. You and the project team decide to use the previous project as a template for your current project. A template can help you and the project team do all of the following except for which one?

    A. Identify typical schedule milestones.

    B. Create parametric estimates for repetitive activities.

    C. Save time creating activity duration estimates.

    D. Import activity attributes.

  • Question 208:

    Diane is the project manager of the HGF Project. A risk that has been identified and analyzed in the project planning processes is now coming into fruition. What individual should respond to the risk with the preplanned risk response?

    A. Diane

    B. Project sponsor

    C. Risk owner

    D. Subject matter expert

  • Question 209:

    Marty is the project manager of the recently completed NHK Project. The project was deemed successful by the project customer and they have signed the formal acceptance documentation. Marty has written the final project report, released the project team, and completed the lessons learned documentation. What else should Marty do in the closure of the NHK Project?

    A. Archive the project records.

    B. Summarize the project risks costs.

    C. Summarize the project variance.

    D. Close the project office.

  • Question 210:

    You are the project manager of the NHG. The following figure represents your project network diagram.

    Management has asked that you add some features to the project scope. Through the change control system these changes are approved and they'll affect Activity I. The duration of Activity I, which is on the critical path, will decrease by three days. What affect does this have on the critical path?

    A. The critical path will now take 26 days.

    B. The critical path will now take 17 days.

    C. The critical path will now take 23 days.

    D. The critical path will now take 20 days.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.