  • Question 241:

    You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure:

    A. Communications bull's eye

    B. Performance goals

    C. Earned value management goals

    D. Project exception report

  • Question 242:

    Amy is working on a project which is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked Amy to report on the schedule variance for her project. If Amy's project has a BAC of $750,000 and she has spent $485,000 to date, what is the schedule variance value?

    A. -$75,000

    B. -$42,000

    C. -$45,000

    D. -$65,000

  • Question 243:

    You are the project manager of a project that has a budget of $675,000 and you have completed 40 percent of the project work. Your project is supposed to be 60 percent complete but you are actually only 40 percent complete. Due to some errors, however, you have actually spent $335,000 of the budget. Management wants to know what the project's cost performance index (CPI) is. What value do you report?

    A. -$135,000

    B. .67

    C. .81

    D. -$65,000

  • Question 244:

    Holly is the project manager for her organization. In her project, she has worked with the project team to define when the project team will be utilized in the project, the duration of the project activities, and the sequence in which the project work must be completed. During several phases of her project, the project team will need to work more than fifty hours per week. The project team members have agreed this is necessary and they're willing to do the work to complete the project. Management, however, has not approved Holly's schedule based on the overtime the scheduling will require. They have set a limit on the project schedule of 45 hours per week. What is this limit technically called? Each correct answer represents a complete solution. Choose all that apply.

    A. Constraint

    B. Assumption

    C. Execution variance analysis

    D. Resource leveling heuristic

  • Question 245:

    You are the project manager of the NHQ project. This project deals with a new technology that your company has never used before. You have petitioned the management to hire a consultant to help you and the project team to create the WBS, the activity list, and complete the duration estimates. The management is concerned about the costs of the consultant, but agrees to your request because of the nature of this new work. The consultant can best be described as what type of resource for this project?

    A. Direct expense

    B. External requirement

    C. Temporary resource

    D. Expert judgment

  • Question 246:

    Samuel works as a project manager in Bluewell Inc. He is performing constructability analysis in one of the initial planning phases. Which of these does constructability take into account during analysis? Each correct answer represents a complete solution. Choose three.

    A. Quality inspections and compliance

    B. Location, logistics, and resource availability analysis

    C. Labor productivity studies from previous similar projects in the area

    D. The average price of general labor in the area

  • Question 247:

    What is the term assigned to graphic in the figure given below?

    A. Communications bull's eye

    B. Performance goals

    C. Earned value management goals

    D. Project exception report

  • Question 248:

    You are the project manager for your organization. You and the project team are developing the project schedule for your current project. In addition to the enterprise environment factors and the organizational process assets, you will need seven other inputs to this process. Which one of the following is NOT an input to the Develop Schedule process?

    A. Resource calendars

    B. Schedule data

    C. Activity list

    D. Project scope statement

  • Question 249:

    Which of the following individuals performs various management roles within an administrative or functional area of the business, such as human resources, finance, accounting, or procurement?

    A. Seller

    B. Operations manager

    C. Functional manager

    D. Project manager

  • Question 250:

    You are the project manager of the OOI Project and you're forty percent complete with this project. The project has a BAC of $2,345,650 and you have spent $950,000 to date. Based on your aggressive scheduling you should at the 45

    percent milestone today, but due to some early delays you're running late.

    What is the schedule variance of your project?

    A. -$29,350

    B. -$117,282

    C. -$938,260

    D. -$11,740

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.