Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Mar 29, 2025

PMI PMI Certifications PMI-SP Questions & Answers

  • Question 251:

    You work as a project manager for BlueWell Inc. Some of the activities in your project are not being completed on time. You review these activities with your project team discovered that the time estimates for the project are much more aggressive than what they are actually experiencing in the completion of the activities. You decide on to create a new schedule for the project. What project management process are you working with when you create a new target schedule?

    A. Estimate activity durations

    B. Estimate activity resources

    C. Control schedule

    D. Develop schedule

  • Question 252:

    Harry works as the project manager for his organization. He is creating the activity list and would like to tag those activities that are comprised of apportioned effort. Which of the following is the best example of apportioned effort?

    A. Adding features to the project's product that is not included in the project scope.

    B. Managing the day-to-day events of a project.

    C. Creating software as defined in the project scope.

    D. Completing project activities as start-to-start events.

  • Question 253:

    You are the project manager for your company. You are working with the management regarding the exact end date of your project. Management needs to know what day of the week your project will complete. Assuming that your project will not require any work to be completed over the upcoming weekends and that the remaining project work will commence on a Tuesday, what day of the week will the project end if there are 67 days of project work left to complete?

    A. Wednesday

    B. Thursday

    C. Monday

    D. Tuesday

  • Question 254:

    Which organizational theory explains the factors that promote performance of people in any organization?

    A. Herzberg's theory

    B. Maslow's Hierarchy theory

    C. McGregor's theory

    D. Expectancy theory

  • Question 255:

    You work as a project manager for BlueWell Inc. Your project requires the project team to paint 1,500 hotel rooms. Your project team reports that it will take them approximately 4 hours to paint each hotel room. You reason, then, that it will take 6,000 hours to paint all of the hotel rooms. What type of an estimate are you creating in this scenario?

    A. Parametric estimate

    B. Definitive estimate

    C. Analogous estimate

    D. Bottom-up estimate

  • Question 256:

    You have been assigned to a project that centers on a discipline you are only topically aware of. While you do have years of experience as a project manager, but you have never worked with the technology, as is in this project. During the define activities process, you rely on your project team and two consultants to coach you and identify the type of activities the project will include. Which tool and technique are you using in the define activities process in this scenario?

    A. Templates

    B. Rolling wave planning

    C. Decomposition

    D. Expert judgment

  • Question 257:

    Tom is the project manager of the HQQ Project. His project has a schedule variance of -$34,500 due to some errors early in the project. Management would like to know how Tom will respond to these variances. What action can help Tom to manage the errors in the project and to ensure that the errors would not occur again?

    A. Lesson learned documentation

    B. Risk analysis

    C. Preventive action

    D. Corrective action

  • Question 258:

    You work as a Project Manager for Dreams Unlimited Inc. You are looking for performance efficiencies of a project. The related key values are provided in the table below:

    MeasurementsValues BCWP (or EV)325 BCWS (or PV) 300 ACWP (or AC)410

    What will be the cost performance index (CPI) of the project at the current point of time?

    A. 0.923

    B. 1.083

    C. 1.261

    D. 0.792

  • Question 259:

    Harry works as a project manager for the NHQ project. His project has a budget of $2,208,456 and is scheduled to last for three years. His project is currently forty percent complete though it should be forty- five percent complete. In order to reach this point of the project, he has spent $725,000. Management needs a performance report regarding the NHQ project. Management is concerned that this project will be over budget upon completion. What is the estimate at completion for this project that Harry will need to report to management?

    A. $1,312,504

    B. $787,504

    C. $1,812,498

    D. $725,000

  • Question 260:

    You are the project manager of the AHQ project. This project is scheduled to last for six months and will require $345,000 to complete. If the project completes earlier than scheduled, your organization will receive a bonus of $5,000 per day of early completion. Management has asked you to develop an aggressive schedule to realize as much of the bonus as possible, but management does not want you to increase the costs of the project beyond $1,000 per day of the bonus realization. Which of the following approaches will likely add costs to the project?

    A. Adding leads to the project work

    B. Fast tracking

    C. Crashing

    D. Using the critical chain method

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.