Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Mar 29, 2025

PMI PMI Certifications PMI-SP Questions & Answers

  • Question 261:

    Nancy is the project manager of the JJJ Project. This project has recently been approved by the project customer as complete so Nancy must now finalize the administrative closure. Nancy needs to create the final project report to report the successes and failures in the project. Who should Nancy deliver this final project report to if she is participating in a projectized structure?

    A. Functional Management

    B. Project sponsor

    C. Whomever the communications management plan directs her to

    D. Project customer

  • Question 262:

    Lily works as a project manager for BlueWell Inc. She has recorded the following duration estimates for an activity in her project: optimistic 35, most likely 50, and pessimistic 95. What time will she record for this activity?

    A. 48

    B. 55

    C. 54

    D. 40

  • Question 263:

    Holly is the project manager for her organization. She is creating the activity list and would like to tag those activities that are comprised of discrete effort. What is discrete effort?

    A. It is a term used to describe activities whose effort cannot be directly measured to the project objectives.

    B. It is a term used to describe activities whose effort can be directly measured and linked to the project objectives.

    C. It is a term used to describe activities that are supportive of the project work, but not linked to the project deliverables.

    D. It is a term used to describe activities that are core project management processes, but not core project activities.

  • Question 264:

    You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone which accounts for half of the project completion. There have been some errors in the project which has caused you to spend $2,073,654. What is this project's schedule performance index?

    A. 1.02

    B. 0.98

    C. 0.90

    D. -$108,120

  • Question 265:

    Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the project costs to date to $1,525,140, but his project is five percent more complete than what was planned. What is the cost variance for this project that Fred needs to report to management?

    A. $122,845

    B. -$51,000

    C. -$85,000

    D. Zero

  • Question 266:

    Which of the following documents is a narrative description of products or services to be supplied by the project and has detailed requirements and pricing specified on it?

    A. Scope of statement

    B. Project charter

    C. Statement of work (SOW)

    D. WBS

  • Question 267:

    The figure given below demonstrates the communication model for a project. What role does the component E play in the communications model?

    A. Static

    B. Deterrent

    C. Noise

    D. Barrier

  • Question 268:

    You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone which accounts for half of the project completion. There have been some errors in the project, which has caused you to spend $2,073,654. What is this project's schedule variance?

    A. -$48,654

    B. 13 percent

    C. -$225,000

    D. 0.98

  • Question 269:

    You have been hired as a project manager for Tech Perfect Inc. You are studying the documentation of planning of a project. The documentation states that there are twenty-five stakeholders with the project. What will be the number of communication channels for the project?

    A. 300

    B. 50

    C. 600

    D. 25

  • Question 270:

    John is the project manager for his organization. He has created a status dashboard for his stakeholders. What is a status dashboard?

    A. It is a report that details the current status of risks and issues.

    B. It is a software application that allows stakeholders to view the project manager's performance.

    C. It is a web-based tool to inspect the project deliverables for performance.

    D. It is a report that reflects the overall performance of scope, schedule, quality, cost, or other project performance metrics.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.