Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Mar 29, 2025

PMI PMI Certifications PMI-SP Questions & Answers

  • Question 271:

    Which of the following individuals has a management role in a core business area, such as research and development, design, manufacturing, provisioning, testing, or maintenance?

    A. Functional manager

    B. Operations manager

    C. Project manager

    D. Seller

  • Question 272:

    A construction company is about to start a new project. It requires hiring a project manager for this project. Which of the following are the most important skills that a person must have to be selected as a project manager?

    A. Problem solving

    B. Team building and human resources

    C. Leading

    D. Communication

    E. Negotiation and influential

  • Question 273:

    Which of the following documents captures and defines the work activities, deliverables, and a timeline that a vendor will execute against in performance of work for a customer?

    A. Project charter

    B. Scope of statement

    C. SOW

    D. WBS

  • Question 274:

    Laura is the project manager for her organization and management has requested her to create a report on her project's performance. Laura needs to analyze her current project performance and then compare it against what, in order to create a performance report?

    A. Cost variances and Cost Performance Index

    B. Scope baseline

    C. Performance measurement baseline

    D. Schedule variances, planned value, and the Schedule Performance Index

  • Question 275:

    Ben is the project manager of the NHF Project for his organization. Some delays early in the project have caused the project schedule to slip by nearly 15 percent. Management would like Ben to find a method to recoup the schedule slippage and to get the project back on track. Management is risk- adverse with this project. Which of the following methods should Ben avoid to recoup the project time?

    A. Crashing

    B. Fast tracking

    C. Critical chain methodology

    D. Adding lead time

  • Question 276:

    John works as a Project Manager for Blue Well Inc. He is measuring cost efficiency of his project. The key values are provided in the table below:

    What is the cost performance index (CPI) of the project at the current point of time?

    A. 0.96

    B. 1.082

    C. 0.833

    D. 1.0625

  • Question 277:

    Beth is the project manager for the NHQ project. This project deals with fiber optic cabling in her organizational campus. Tim is the electrical engineer for her company and is the only internal resource that can complete several of the project activities that deal with the fiber optic cables. Because Tim is a highly- skilled resource, he is already scheduled on several projects within the organization and is not available when Beth needs him to complete some of the project activities. This is an example of which term?

    A. Resource calendar conflict

    B. Matrix network

    C. Organizational process assets

    D. Activity resource requirements

  • Question 278:

    Which of the following are the inputs to the Develop Project Charter process? Each correct answer represents a complete solution. Choose all that apply.

    A. Procurement document

    B. Contract

    C. Business case

    D. Project statement of work

  • Question 279:

    John works as the project manager for Honeywell Inc. He is involved in the periodic collection and analysis of baseline versus actual data to understand and communicate the project progress. Which of the following techniques is used in generating performance reports?

    A. Work performance information

    B. Change requests

    C. Work performance measurements

    D. Forecasting method

  • Question 280:

    You are the project manager of the NHQ project. Your project has a budget of $1,258,456 and is scheduled to last for three years. Your project is currently forty percent complete though it should be forty- five percent complete. In order to reach this point of the project, you have spent $525,000. Management needs a performance report regarding the NHQ project. Management is concerned that this project will be over budget upon completion. What is the estimate at completion for this project that you will need to report to management?

    A. -$62,922.80

    B. $1,312,504

    C. $1,525,000

    D. $787,504

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.