Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Mar 29, 2025

PMI PMI Certifications PMI-SP Questions & Answers

  • Question 301:

    You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450. What is this project's to- complete performance index based on the current BAC?

    A. 1.02

    B. 0.010

    C. 0.75

    D. 0.95

  • Question 302:

    You work as a project manager for BlueWell Inc. Management has asked you not to communicate performance unless the CPI is less than 0.96 or the SPI dips below 0.98. What type of report would you create for management, if these instances develop in your project?

    A. Cost variance report

    B. Exceptions report

    C. Performance management report

    D. Schedule variance report

  • Question 303:

    Sam is the project manager of the NQQ project. He and the project team have completed the stakeholder identification process for his project. What is the main output of the identify stakeholders process?

    A. Communications management plan

    B. Stakeholder register

    C. Requirements

    D. Stakeholder management strategy

  • Question 304:

    You are the project manager of the BHG Project. You are creating a network diagram as shown in the figure: Mary, a project team member, reports that an identified risk is likely to happen in the project that will affect the completion date of Activity D . She reports that the risk event will likely cause the duration of the activity to increase by six days. If this happens what is the earliest the project can complete?

    A. 32 days

    B. 29 days

    C. 27 days

    D. 26 days

  • Question 305:

    Mark is the project manager of the GHQ Project. He is happily reporting that his project has a schedule performance index of 2.12. Management, however, does not think this is good news. What is the most likely reason why management does not like an SPI of 2.12?

    A. It is not good news because a larger number means the schedule duration estimates were likely to be wrong to begin with.

    B. They likely do not understand the SPI formula.

    C. It is not good news, as the number should be closer to 100 than 0.

    D. It is good news, but Mark may have large cost variances to achieve this value.

  • Question 306:

    You are the project manager of the NHA Project. This project is expected to last one year with quarterly milestones throughout the year. Your project is supposed to be at the third milestone today but you're likely only 60 percent complete. Your project has a BAC of $745,000 and you've spent $440,000 of the budget- to-date. What is your schedule performance index for this project?

    A. 80

    B. 1.02

    C. 102

    D. 0.80

  • Question 307:

    Which one of the following estimate types is a form of expert judgment?

    A. Parametric estimate

    B. Analogous estimate

    C. Bottom-up estimate

    D. Definitive estimate

  • Question 308:

    You are the project manager of the NHQ Project. Management has set a conformance to the project schedule for your project at 0.95. What does this term mean?

    A. It means the largest schedule variance you can have is five percent.

    B. It is the earned value divided by the planned value for your project.

    C. It is the expectation of management to be 95 on schedule at 95 percent of the project.

    D. It means you will need to earn at least 95 cents per dollar invested in the project.

  • Question 309:

    George is the project manager of the NHQ Project and has a budget of $778,000. The project is scheduled to last for one year with an equal amount of work completed each quarter. The second quarter of the project has ended and George has spent $325,000 but has only finished forty percent of the project. Management needs a variance report for the project schedule. What value should George report in this instance?

    A. .96

    B. -$77,800

    C. $-34,500

    D. -$13,800

  • Question 310:

    You are the project manager of the GHY Project. Management wants you to create a process improvement plan for your project. Your project will be studied by management and will become a standard for all future organizational projects based on your project's performance, approach, and implementation of project processes. All of the following should be included in your project's process improvement plan except for which one?

    A. Process boundaries

    B. Process configuration

    C. Targets for improved performance

    D. Identification of project risks

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.