Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :

PMI PMI Certifications PMI-SP Questions & Answers

  • Question 51:

    You are the project manager of the MQQ project. Unfortunately, this project is not performing well and you must do something to address the problems in your project. Based on your planning for monitoring and controlling project performance, you know that there are three outputs of performance reporting. Which one of the following is the only output that is most appropriate for this poorly performing project?

    A. Organizational process assets update

    B. Performance reports

    C. Performance re-baselining

    D. Change requests

  • Question 52:

    You are the project manager of the NHQ project. This project is slightly larger than the TR project, in which you also served as the project manager. You decide to use the actual activity duration of the GTR project as a basis for your current NHQ project. This, you reason, will save time for your project, as the previous project has provided the information. Which one of the following terms best describes the action you are doing in this scenario?

    A. You are creating an analogous estimate.

    B. You are creating a bottom-up estimate.

    C. You are relying on expert judgment.

    D. You are creating a rough order of magnitude estimate.

  • Question 53:

    You have 83 project stakeholders from all across your organization. Some of the stakeholders, such as functional management, require weekly communication from you, while other stakeholders, such as the end users, only need quarterly progress updates. Where can you record this communication requirements based on your stakeholder analysis?

    A. Project communications management plan

    B. Project reporting structure

    C. Project schedule

    D. Project scope management plan

  • Question 54:

    Amy works as a project manager for BlueWell Inc. Her organization wants her to create a new warehouse. Which of the following documents will she create to define the business needs, the project justification, and the current requirements?

    A. Project scope

    B. Feasibility study

    C. Project charter D. Work breakdown structure

  • Question 55:

    You are the project manager for your organization. Maagement has asked you for this current project. You use the critical chain method to create the project network diagram rather than the more traditional critical path method. What is the critical chain method?

    A. It examines only the non-critical path activities that are considered near critical, if the float is one day or less.

    B. It examines only the critical path activities to determine when the project completion date may be.

    C. It examines the availability of needed project resources to determine when activities may actually happen.

    D. It generates a Gantt chart that reflects the availability of project resources and considers working and non-working days for the project.

  • Question 56:

    You work as a project manager for BlueWell Inc. By referring to the figure given below, you along with your project team is calculating the latest completion of an activity.

    What is the latest your project team can complete Activity I?

    A. Day 29

    B. Day 26

    C. Day 25

    D. Day 30

  • Question 57:

    You are the project manager of the NHQ project. This project is currently running about 15 percent behind schedule and the management has asked you to rectify the problem. You have elected to crash the project. What does this term mean?

    A. Reject all proposed change requests for the project.

    B. Add resources to the project work.

    C. Add cost to the project budget.

    D. Cut non-value added activities to the project.

  • Question 58:

    You are the project manager of the NHQ Project. This project has a Budget at Completion of $750,000 and is expected to take 18 months to complete. The project is supposed to be 75 percent complete, but due to some errors the project is only 60 percent complete. At this time the project has spent $465,500. Management has asked you to review the project work and report the project's SPI. What is the SPI for this project?

    A. 0.97

    B. 0.80

    C. $562,500

    D. -$112,500

  • Question 59:

    Which of the following is an output of the Develop Project Charter process?

    A. Enterprise environmental factors

    B. Contract

    C. Business case

    D. Project charter

  • Question 60:

    You are the project manager for GGY Project. You are working with your project team to record the actual durations for the activities they have completed in the project schedule. Mary, one of your project team members, wants to know why you need to know how long it actually took the project team to complete their assignments as long as the project work is completed. Which of the following is the best response for Mary's query?

    A. Actual durations need to be recorded to track process improvement.

    B. Actual durations need to be recorded to create the schedule baseline.

    C. Actual durations need to be recorded to measure the actual progress of the project.

    D. Actual durations need to be recorded to perform quality control on the project management processes.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.