Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Mar 29, 2025

PMI PMI Certifications PMI-SP Questions & Answers

  • Question 61:

    A project manager is reviewing her project performance. Her project has a BAC of $950,000 and is currently 40 percent complete, though it was scheduled to be 45 percent complete at this time. Her project has spent $387,526. Management would like to know if there is a schedule variance. What is the planned value for this project?

    A. -$47,500

    B. 0.89

    C. $427,500

    D. 0.98

  • Question 62:

    You work as a project manager for BlueWell Inc. You must communicate on a regular basis with all of your project stakeholders. In your project, you have 755 stakeholders. How many communication channels exist in the project?

    A. 284,635

    B. 570,025

    C. 569,270

    D. 755

  • Question 63:

    You work as a scheduler for your organization. You are developing a schedule and its constraints for the SAP project. There are nine inputs to develop a project schedule. Which of the following is NOT an input to the schedule development process?

    A. Work breakdown structure

    B. Activity attributes

    C. Resource calendars

    D. Activity list

  • Question 64:

    The figure given below demonstrates the communication model for a project. What role does the component D play in the communication model?

    A. Sender

    B. Medium

    C. Encoder

    D. Transporter

  • Question 65:

    You are the project manager of the GYG Project. A new scope change is being considered for your project. You are concerned, however, that the scope change may add costs, risks, and adversely affect the project schedule. What project management process is responsible for evaluating the full effect of a proposed scope change on your project?

    A. Scope change control

    B. Schedule change control

    C. Integrated change control D. Change Control Board approval process

  • Question 66:

    You are the project manager of the NNN Project. Stakeholders in the two-year project have requested to send status reports to them via email every week. You have agreed and are sending the reports on each Thursday. After six months of the project, the stakeholders are pleased with the project progress and they would like you to reduce the status reports to every two weeks. What process will examine the change to this project process and implement it in the project?

    A. Project change control process

    B. Perform integrated change control process

    C. Configuration management

    D. Communications management

  • Question 67:

    You are the project manager of the NNN Project. Stakeholders in the two-year project have requested to send status reports to them via email every week. You have agreed and are sending the reports on each Thursday. After six months of the project, the stakeholders are pleased with the project progress and they would like you to reduce the status reports to every two weeks. What process will examine the change to this project process and implement it in the project?

    A. Project change control process

    B. Perform integrated change control process

    C. Configuration management

    D. Communications management

  • Question 68:

    Harry works as a project manager for BlueWell Inc. He is determining the budget of the project. According to the PMBOK, there are seven inputs to this process. Which one of the following is NOT an input to the determine budget process?

    A. Contract

    B. Reserve analysis

    C. Scope baseline

    D. Project schedule

  • Question 69:

    Robert is the project manager for his organization. Management has asked Robert to provide them with the metric he uses to measure deliverables status, costs incurred, and especially how he measures the schedule progress for schedule adherence. What project component could Robert provide for management?

    A. Milestone list

    B. Cost management and the project schedule

    C. Work performance measurements

    D. Project management plan

  • Question 70:

    You are the project manager for the NGH project. The figure given below represents the small project you are completing for your organization.

    How much float can you use on Activity G if Activity B actually takes eight days to complete?

    A. Four

    B. Three

    C. Seven

    D. Zero

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.