Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Mar 29, 2025

PMI PMI Certifications PMI-SP Questions & Answers

  • Question 71:

    You are the project manager for your organization. You are working with your project team to develop the project schedule. You would like to automate much of the scheduling by using Microsoft project. Microsoft project as a scheduling tool is an example of what tool and technique for the Develop Schedule Process?

    A. Organizational process asset

    B. Scheduling tool

    C. Project Management Information System

    D. Project office software

  • Question 72:

    You are the project manager for your organization. You are working through the control schedule process. According to the PMBOK, there are four inputs to this process. Which one of the following is NOT an input to the control schedule process?

    A. Schedule data

    B. Work performance information

    C. Project management plan

    D. Project schedule

  • Question 73:

    What is the formula to find the schedule performance index?

    A. EV-PV

    B. EV/AC

    C. EV/PV

    D. EV-AC

  • Question 74:

    Kay is the project manager of the QUI Project. This project is done but is also considerably over budget. Kay has elected to crash the project in order to recoup schedule delays but this increased the project costs. What should Kay do with the information regarding the schedule delays and cost overruns?

    A. Create an entry in the lessons learned documentation and explain her reasoning behind the corrective actions.

    B. Create an exceptions report.

    C. Create a variance report.

    D. File the information as part of the project final report.

  • Question 75:

    You work as the project manager for BlueWell Inc. Mark, a project team member, has some doubts related to the outputs of the control schedule process. Which of the following is an output of the control schedule process?

    A. Project schedule

    B. Lessons learned

    C. Change request

    D. Activity resource requirement

  • Question 76:

    You are the project manager of the QAQ Project. The QAQ Project has a BAC of $2,786,121. You are currently 20 percent complete with this project, though you should be 25 percent complete with the project work. The project has consumed $595,000 of the project budget to date. Management has asked you, based on the current project performance, what the project's estimate to complete will be considering the current project schedule variance. What is the ETC for this project?

    A. $2,975,000

    B. 1.02

    C. $139,306

    D. $2,380,000

  • Question 77:

    Which of the following allows activities to be done in parallel that would normally be done in sequence?

    A. Lag time

    B. Lead time

    C. Fast tracking

    D. Crashing

  • Question 78:

    You are the project manager for your organization. You have created the project schedule and have presented it to the management for their approval. Management decides to enforce resource leveling heuristics on your project schedule. What will likely happen to your project now?

    A. It will require fewer resources due to the cut in the project scope.

    B. It will require additional resources for the additions to the project scope.

    C. It will require additional resources if it is to finish in the same amount of time, as originally predicted.

    D. It will require a new scope baseline to reflect the management change in the project approach.

  • Question 79:

    Alicia works as a project manager for NacTec project. She is undergoing the project monitoring phase in her project. Which of the following will she choose to accomplish the task? Each correct answer represents a complete solution. Choose all that apply.

    A. Reports

    B. Meetings

    C. Diaries

    D. Future planning

  • Question 80:

    You are the project manager for your project. Your project is scheduled to last for one year and you are currently forty percent complete with the project. Based on your current performance measurements you have an SPI of .95 and a cost variance of -$24,000. You need to report this information to the management, but you will also need a solution to present with the variance information. Which one of the following can you present to the management as a part of the control schedule tools and techniques for variances?

    A. Work performance measurements

    B. Corrective actions

    C. Trim the project scope

    D. Causes of variances

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.