Which one of the following would NOT typically be part of procurement?
A. Estimating.
B. Engagement of external suppliers.
C. Definition of items to be acquired.
D. Bidding.
The business case is owned by the project:
A. manager.
B. sponsor.
C. steering group (board).
D. senior user.
In project management quality is best defined as:
A. inspection, testing and measurement.
B. reviews and audits.
C. fitness for purpose of deliverables.
D. professionally-bound project reports.
Which one of the following statements is correct?
A. Independent reviews and quality audits form part of quality assurance to ensure the project manager delivers on time and to budget.
B. Quality assurance provides confidence to stakeholders that requirements for quality will be exceeded.
C. Quality control verifies that the project deliverables conform to specification, are fit for purpose and meet stakeholder expectations.
D. Quality planning enables the project manager to manage the trade-off between customer expectations and budget.
Estimating by using historical information is known as:
A. comparative estimating.
B. parametric estimating.
C. bottom-up estimating.
D. strategic estimating.
Which one of the following is the correct definition of an issue?
A. Any major problem that the project team has to deal with.
B. A problem that is the responsibility of the Project Manager.
C. An uncertain event that should it occur would have an effect on project objectives.
D. A threat to project objectives that cannot be resolved by the Project Manager.
Which one of the following best describes the entire project reporting process?
A. Producing an exception report to communicate a project issue to the project board.
B. Publicising the project benefits to the business organisation.
C. Notifying team members of the project's progress at the weekly team meeting.
D. Formally notifying the status of the project to the project's stakeholders.
Resource levelling seeks:
A. to schedule activities within the limits of their float.
B. to minimise the use of overtime and weekend working.
C. not to exceed the limits of resource available.
D. to increase the resource availability
Which one of the following statements best describes resource scheduling?
A. A process which identifies activities that will need project resources.
B. A process to assign roles to project resources.
C. A process that identifies when resources are needed.
D. A process to estimate the project resources.
Which structure shows the reporting relationships and communications channels for a project?
A. Work breakdown structure.
B. Organisational breakdown structure.
C. Product breakdown structure.
D. Responsibility assignment structure
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only APM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-PFQ exam preparations and APM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.