Which statement best describes a responsibility of the project manager:
A. to be the sole source of expertise for estimating techniques on cost and time.
B. to deliver the project objectives to enable benefits to be realised.
C. to take ultimate accountability for the delivery of the business benefits.
D. to delegate all accountability for managing time, cost and quality to team leaders
Which one of the following best describes users?
A. Providers of both strategic and tactical direction to the project.
B. Those intended to receive benefits or operate outputs.
C. Facilitators of an appropriate issue resolution procedure.
D. Those providing full-time commitment to the project.
Who owns the Project Management Plan (PMP)?
A. The project team.
B. The chief executive.
C. The project manager.
D. The project support office
Which one of the following statements is true?
A. The business case is owned by the sponsor and is created during the concept phase of the project life cycle.
B. The business case is owned by the project manager and is created during the concept phase of the project life cycle.
C. The business case is owned by the sponsor and is created during definition phase of the project life cycle.
D. The business case is owned by the project manager and is created during the definition phase of the project life cycle.
Which one of the following is a valid project Key Performance Indicator (KPI)?
A. Staff appraisals.
B. Management buy in.
C. Milestone achievement.
D. Master schedule.
Which one of the following is least likely to be a success criteria?
A. A target for the project to receive zero change requests.
B. The date by which the project is to be completed.
C. Delivery of products that meet required specifications.
D. The awarding of bonuses to senior management.
Which one of the following statements best defines the purpose of a Product Breakdown Structure (PBS)?
A. To define the hierarchy of deliverables that are required to be produced on the project.
B. To define how the products are produced by identifying derivations and dependencies.
C. To establish the extent of work required prior to project commissioning and the handover.
D. To identify the health and safety strategies and procedures to be used on the project.
Scheduling can best be defined as the process used to determine:
A. overall project duration.
B. project cost estimating.
C. the project management plan.
D. sub-contractor's responsibilities
Which one of the following statements is true?
A. An increase in project scope is likely to increase project cost.
B. A decrease in the project time is likely to increase project quality.
C. An increase in the project quality requirements is likely to decrease project cost.
D. A decrease in the project cost is likely to decrease project time.
Which one of the following best describes a project issue?
A. A major problem that requires formal escalation.
B. A problem that the project manager has to deal with on a day-to-day basis.
C. An uncertain event that may or may not occur.
D. An opportunity that occurs through change control.
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only APM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-PFQ exam preparations and APM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.