  • Question 271:

    Which of the following are typical estimating methods? 1) Analytical 2) Budgeting 3) Analogous 4) Parametric

    A. 1, 2 and 4

    B. 1, 2 and 3

    C. 1, 3 and 4

    D. 2, 3 and 4

  • Question 272:

    Which of the following define leadership? 1) Ability to establish vision and direction 2) Developing team skills that enhance project performance3) Empowering and inspiring people to achieve success 4) Ability to influence and align others towards a common purpose

    A. 1, 2 and 4

    B. 1, 2 and 3

    C. 2, 3 and 4

    D. 1, 3 and 4

  • Question 273:

    Which of the following defines the term 'issue'?

    A. A problem which is now or is about to breach delegated tolerances for work on a project or programme.

    B. A problem which occurs on a day-to-day basis which could have an immediate impact on a project.

    C. A problem which has the potential to impact on the achievement of specific project objectives.

    D. A problem which can only be resolved by a project manager and within the project team

  • Question 274:

    Suppliers are stakeholders of a project management plan because they:

    A. contribute to the project's procurement strategy.

    B. help satisfy the project's resource requirements.

    C. provide acceptance certificates based on quality of resources supplied.

    D. determine the quality requirements of goods supplied.

  • Question 275:

    Which of the following defines the term 'risk'?

    A. The potential of a situation or event to impact on the achievement of specific objectives.

    B. A problem that is now or is about to breach delegated tolerances for work on a project or programme.

    C. Scope creep within an uncontrolled project.

    D. The use of estimation to determine costs, resources and activities.

  • Question 276:

    Which of the following is a difference between deployment baselines in linear life cycles and iterative life cycles?

    A. Linear project life cycles set the deployment baseline for the whole project.

    B. In an iterative project life cycle the scope and quality are fixed in the deployment baseline.

    C. Only deployment baselines in iterative life cycles have an integrated baseline review.

    D. Only deployment baselines in linear life cycles have an integrated baseline review

  • Question 277:

    One aspect of quality planning is to:

    A. plan the audit of a project to provide assurance to the project board.

    B. provide confidence that a project will achieve its objectives in the required time frame.

    C. specify the acceptance criteria used to validate the outputs are fit for purpose.

    D. confirm routes for reporting to ensure effective communication

  • Question 278:

    Which of the following is not a key element of project scope management?

    A. Define outputs.

    B. Identify outputs.

    C. Share outputs.

    D. Control outputs

  • Question 279:

    An extended project life cycle can be defined as:

    A. an approach that adds operational and termination phases to a linear life cycle.

    B. an approach that adds adoption and benefits realisation phases to a linear life cycle.

    C. a framework for conducting a cost-benefit analysis once a project has closed.

    D. a framework for ensuring the re-deployment of assets post project.

  • Question 280:

    A project manager requires a team member to focus on the team's objectives and draw out other team members. Which of the Belbin's team roles is most appropriate?

    A. Shaper.

    B. Monitor evaluator.

    C. Specialist.

    D. Co-ordinator

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only APM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-PFQ exam preparations and APM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.