Which of these is a correct definition of an Estimate?
A. The use of a range of tools and techniques to produce forecasts of the probable time or cost of completing work
B. An educated guess that improves over time
C. A forecast of the probable time or cost of completing work
D. An estimate is an approximation of project time and cost targets that forms the basis of the contract
In which phase of the project should the Procurement Strategy be written?
A. Concept
B. Definition
C. Deployment
D. Transition
In developing a network the first task after listing the activities is to...
A. Define activity durations
B. Determine float
C. Determine the interdependencies of activities
D. Harmonise the activity to a calendar
Configuration management would be used to:
A. ensure the required materials are in stock when needed.
B. help the impact Of a change request to be fully assessed.
C. help configuration within IT projects.
D. ensure that a work breakdown structure can be completed.
Who is primarily responsible for configuration management in the project?
A. Project manager,
B. Risk manager.
C. Quality manager.
D. The project team.
The prime purpose of configuration management is to:
A. ensure the traceability and integrity of the delivered product or products
B. minimise the impact of changes on the scope of the project
C. ensure that the final product meets the needs of the business as defined by key stakeholders.
D. maximise the impact of agreed enhancements to the project deliverables
What is the key benefit of having configuration management in the project?
A. It allows a thorough assessment of the factors that are most likely to affect the change.
B. It means to justify to the customer variances from the original objectives.
C. It ensures that the delivered product most closely meets the needs of the customer.
D. It manages the impact of change to the project scope.
What is the main reason for an initial high-level review of a change request?
A. To consider if the change is feasible to evaluate at this stage.
B. To establish who might be the best stakeholders to be involved in the change.
C. To ensure that the change request is considered as soon as possible.
D. To implement the necessary actions to ensure the change has a smooth implementation.
What action is essential after a change has been approved?
A. The highlights of the change are communicated directly to the sponsor.
B. The actual impact of the change is assessed.
C. The next change requested should be reviewed as quickly as possible.
D. The related plans must be updated to reflect the change.
A formally constituted group of stakeholders responsible for approving or rejecting changes to the project baselines, is referred to as the:
A. change management committee,
B. change authority,
C. change control board.
D. change implementation group.
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only APM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-PFQ exam preparations and APM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.