Which options do you have to plan both quant ties and capacities during line loading in repetitive manufacturing? (Choose 2)
A. Run MRP with quota arrangement.
B. Run MRP with automatic selection of production version.
C. Assign planned orders manual lying the planning table.
D. Run PP/DS heuristics for repetitive manufacturing.
Which materials have a negative quantity in a bill of materials or in a recipe? (Choose 3)
A. Bulk materials
B. Co-products
C. By-products
D. Waste products
E. Continuous flow materials
Your client is asking for your advice on material master numbering in SAP S/4HANA. What do you need to consider? (Choose 2)
A. The maximum mater all number length is 40 for external numbers and 18 for internal numbers
B. The number of leading zeros for internal numbers is client-specific.
C. In Customizing you can decide by material type whether to use the long material number.
D. The display template for material numbers applies to all clients.
Which times elements does MRP consider in backward scheduling to determine he order dates for components from dependent requirements? (Choose 2)
A. Planed delivery time
B. Operation duration
C. In-house production time
D. Total replenishment lead time
What does it mean for the production planner when MRP works with infinite capacities?
A. MRP assigns capacity requirements automatically after the last scheduled order on a work center.
B. MRP creates capacity requirements without checking the capacity of a work center.
C. MRP assigns capacity requirements automatically to work center is with the earliest available capacity.
D. MRP creates capacity requirements only if the work center has sufficient capacity.
What is the purpose of a reporting point confirmation in repetitive manufacturing? (Choose 2)
A. To stage different components for a production line simultaneously
B. To determine the work in progress along the production line
C. To reduce the total production lead time for along production line
D. To provide timely updates of inventory management for the staged components
You want to create a production order from a planned order. What methods could you use? (Choose 2)
A. Combined conversion
B. Partial conversion
C. Collective conversion
D. Order release
How can you carry out cost object controlling for production orders? (Choose 2)
A. Milestone-related
B. Cost-related
C. Product-related
D. Order-related
Which of the following processes lead to an entry in the MRP planing file? (Choose 3)
A. Change of the material's procurement type
B. Creation of purchasing contract
C. Creation of dependent requirements
D. Creation of sales order
E. Change of the storage bin
What do you use to dispatch operations from planned orders so that the production plan can be fulfilled?
A. Material Requirements Planning (MRP)
B. Capacity Requirements Planning (CRP)
C. Supply Network Planning (SNP)
D. Demand Planning (DP)
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TS422_2021 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.