  • Question 61:

    In your project, you have several materials that are planned by different people. How can you assign the planning responsibility?

    A. MRP type

    B. MRP group

    C. MRP planning file

    D. MRP controller

  • Question 62:

    You are working with planning strategy 40 (Planning-with-final assembly).

    When does consuption of planned independent requirements take places?

    A. When you deliver a sales order

    B. When the MRP result are saved

    C. When you create a sales order

    D. When you create a planned order

  • Question 63:

    You want to set up a make-to-order planing scenario for finished material. The bil of material contains two components: one should be procured for each sales order individually, the other one shold be procured jointly for all independent requirements. Forcasting for the finished product is NOT possible. Which setting do you make to achive this?

    A. Choose planning strategy 50 (Planning whthout final assembly) and select corresponding Mixed MRP indicator

    B. Choose planning strategy 20 (Make-to-order) and select corresponding Invidual/collective indicator

    C. Choose planning strategy 20 (Make-to-order) and select corresponding Mixed MRP indicator

    D. Choose planning strategy 50 (Planning whthout final assembly) and select corresponding Invidual/collective indicator

  • Question 64:

    What does forecasting in demand planning cycle include? (Choose 3)

    A. Past quotation quantities

    B. Past sales order quantites

    C. Market intelligence

    D. One-off events

    E. Past procurment quantities

  • Question 65:

    You want to use capacity availability checks for production orders. Which settings have to be made for this? (Choose 2)

    A. A checking rule must be assigned in the checking control

    B. The PRT Availability Check must be set in the checking control.

    C. An overall profile must be assigned in the checking control.

    D. The Relevant for Finite Scheduling indicator must be set

  • Question 66:

    Why would you use phantom assemblies? (Choose 3)

    A. To simplify the structure of bills of materials

    B. To make the assignment of components easier

    C. To reduce the number of changes required in bills of materials

    D. To reduce the number of material masters

    E. To increase the number of planning levels

  • Question 67:

    When working with bouth cross-plant and plant-specific material statuses n the material master, which statuses has the higest priority?

    A. The cross-plant status

    B. The plant-specific status

    C. The last restrictive status

    D. The most restrictive status

  • Question 68:

    What is a work center hierarchy in planning in SAP S/4HANA?

    A. A group of alternative work centers providing a cumulative available capacity for production.

    B. A group of alternative work centers for production, structured in hierarchy levels by priorities

    C. A group of work centers in a production line being used in sequence for production

    D. A group of work centers in a parallel sequence that is used to split production quantities and work on them in parallel

  • Question 69:

    An issue storage location was NOT found through the work center, bill of material(BOM) item, or material master. What determines whether the storage location can be derived from the production version?

    A. MRP group

    B. Plants parameters

    C. MRP controller

    D. MRP profile

  • Question 70:

    Which actions does the system preform by default when you save a confirmation for a finished product in repetitive manufacturing? (Choose 3)

    A. Posting of production costs to the production cost collector

    B. Material staging for nex order in sequence

    C. Archiving of documents for assembly scrap

    D. Posting of goods receipt for the product

    E. Reduction of associated capacity requirements

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TS422_2021 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.