An enterprise wants to use SAP ECC requirements planning together with the NETPL procedure (net change planning in the planning horizon). The planning horizon should be set equally for all materials by default. However, some materials need to have a different planning horizon.
Which procedure do you recommend for setting the planning horizon?
A. Set the planning horizon in the MRP groups in Customizing and store deviant entries in the material masters for the corresponding materials.
B. Set the planning horizon in the plant parameters in Customizing and store deviant entries in the material masters for corresponding materials.
C. Set the planning horizon in the MRP groups and assign deviant entries via the plant parameter settings in Customizing.
D. Set the planning horizon in the plant parameters in Customizing and assign deviant entries via the MRP groups for the corresponding materials.
Which option for selecting a routing exists when you create a production order?
A. Automatic selection of a reference operation set
B. Manual selection based on settings in the order type-dependent parameters
C. Automatic selection based on the selection ID in the material master
D. Manual selection based on the list of routings maintained in the material master
Which of the following requirements is supported by using process orders?
A. Linkage of documents to orders
B. Use of production/resource tools
C. Documentation of the production using an electronic batch record
D. Use of reference operation sets
In which of the following objects can you activate backflushing of components if you want to use this functionality during order confirmation? (Choose three.)
A. Work Center
B. Production Scheduling Profile
C. Material Master (Finished Product)
D. Routing
E. Material Master (Component)
Which of the following functions does SAP Supply Chain Management (SCM) offer?
A. Product development, safety, quality, and maintenance
B. Planning of supply chains across company boundaries
C. Communication with customers through different interaction channels
D. Optimization of the procurement strategy with the supplier pool
Which of the following properties applies to multi-site planning in SAP ECC?
A. When using one-step stock transfer posting, transfer stock is created in the receiving plant.
B. Multi-site planning can be activated using the corresponding planning strategy.
C. Both withdrawal from an alternative plant and stock transfer from another plant are defined via special procurement keys.
D. The use of "scope of planning" is always mandatory for multi-site planning.
In SAP ECC, you want to map an in-house production process for general warehouse production. The fields in the area of the lot size-dependent in-house production time are to be populated when the material master for the final product is created. These fields can be maintained by updating from the scheduling result for the associated routing. You now think that there could be significant changes to the production times in the routing and decide against updating the material master. What problem could this lead to?
A. Subsequent capacity planning is no longer possible due to the obsolete scheduling parameters.
B. Requirements planning runs up against an exception message in basic dates scheduling because the material master parameters do not match the scheduling result from the routing.
C. In the course of basic dates scheduling with requirements planning, dependent requirements request the components from the bill of materials at the wrong times.
D. Lead time scheduling, which occurs by the time that a planned order is converted into a production order (at the latest), cannot take place on the basis of incorrect basic dates.
You have maintained planning strategy group 10 (make-to-stock production) in the material master (SAP ECC) of a material. For the coming months, you have planned requirements with requirement type LSF (derived from main strategy 10). Now, you want to change the requirement type from LSF to VSF (in accordance with planning strategy 40, planning with final assembly) for requirements in the existing production plan.
Which of the following scenarios are applicable in this case? (Choose two)
A. You can enter the strategy group 40 in the material master, but the requirement type is not changed automatically for existing requirements.
B. You must change the requirement type for planning strategy 10 to VSF in Customizing. The requirement type for all existing requirements is then changed by the next planning run.
C. You can change the strategy group from 10 to 40 for the existing production plan in the material master, and the requirement type for all requirements is changed automatically.
D. You can enter the strategy group 40 in the material master and change the present requirement for the product manually in the production plan.
Which of the following organizational efforts can be minimized using the KANBAN procedure?
A. Effort for material staging
B. Effort for capacity planning
C. Effort for Sales and Operations Planning (SOP)
D. Effort for master data maintenance
Which issue can occur if the lot size-dependent in-house production time in the material master is not updated after changing the routing?
A. Lead time scheduling cannot take place.
B. Dependent requirements request the components from the bill of materials at wrong times when using basic dates scheduling.
C. Requirements planning creates an appropriate exception message in basic dates scheduling.
D. Subsequent capacity planning is no longer possible due to the obsolete scheduling parameters.
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TSCM42_67 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.