  • Question 91:

    You want to enhance the system statuses of a production order with user statuses.

    How do you do this?

    A. Define the user statuses in the order type-dependent parameters.

    B. Define a status profile in Customizing and assign it to the production scheduling profile.

    C. Define a status profile in Customizing and assign it to the order type.

    D. Define the user statuses in the Customizing table of the system statuses.

  • Question 92:

    In SAP ECC, you calculate the standard available capacity for a work center capacity using the following data:

    -Start: 7:00:00 a.m.

    -End: 3:00:00 p.m.

    -Break duration: 1 hour

    -Rate of utilization: 80%

    -Overload: 110%

    -

    Number of individual capacities: 1 How large is the standard available capacity?

    A.

    8 hours

    B.

    5.6 hours

    C.

    6.16 hours

    D.

    7 hours

  • Question 93:

    Which data forms the basis for calculating the capacity requirement for an operation? (Choose three.)

    A. Standard values (routing)

    B. In-house production time (material master)

    C. Transport time (routing)

    D. Formulas (work center)

    E. Operation control key (routing)

  • Question 94:

    What could be a consequence of confirming an operation?

    A. The planned costs are updated

    B. The capacity requirements are updated

    C. The production order is rescheduled

    D. The actual costs are settled

  • Question 95:

    What features related to process orders can be used to fulfill Good Manufacturing Practices (GMP) requirements? (Choose three)

    A. Approved master recipes

    B. Digital signature

    C. Electronic batch record

    D. Availability check

    E. Resource selection

  • Question 96:

    What are the names of the objects for process integration of production orders? (Choose two)

    A. Control recipes

    B. Work instructions

    C. PI sheets

    D. Control instructions

  • Question 97:

    You want to use the different options for planning in SAP ECC. What is the correct sequence of the planning procedures?

    A. Sales and operations planning -> Demand management -> Long-term planning -> Material requirements planning -> Capacity planning

    B. Demand management -> Sales and operations planning -> Capacity planning -> Long- term planning > Material requirements planning

    C. Material requirements planning -> Demand management -> Sales and operations planning -> Longterm planning -> Capacity planning

    D. Long-term planning -> Sales and operations planning -> Demand management -> Material requirements planning -> Capacity planning

  • Question 98:

    When analyzing the SAP ECC order report for a planned order for a finished product, you discover that one of the assemblies will not be available in time for the scheduled final assembly because of automatic forward scheduling.

    Which planning procedure do you use to create a feasible production plan from a requirements planning perspective?

    A. Total planning online

    B. Multi-level single-item planning with the "display material list" option

    C. Interactive single-item planning for the delayed assembly

    D. Multi-level single-item planning with the "simulation mode" option

  • Question 99:

    In your company planning strategies are used in the SAP-ECC demand management that are based on consumption. Which of the following statements about consumption is true? (Choose two.)

    A. A consumption situation is dynamic and is always restructured with the planning run.

    B. Consumption can also take place between order reservations and planned independent requirements, depending on the strategy.

    C. Consumption always takes place on the material level between the planned independent requirements and the planned orders.

    D. The consumption parameters (consumption mode and consumption interval) can be set in the material

    master or in the MRP group.

  • Question 100:

    Which objects can affect the calculation of capacity requirements for an operation? (Choose three)

    A. Standard values (routing)

    B. In-house production time (material master)

    C. Transport time (routing)

    D. Formulas (work center)

    E. Operation control key (routing)

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TSCM42_67 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.